MGMT 645 Week 2 Project Charter and Proposal Example

Reviewed by Thomas Kerrigan, MBA, CPA · Liberty University · Updated

This MGMT 645 Week 2 sample is the Project Charter and Proposal, the 100-point first stage of the project that runs through Liberty University MGMT 645 Quality Management, an MS in Project Management course, drafted with chapter 4 of the PMBOK Guide and chapter 3 of Rose. The guide asks for a charter that sets out the business case, goals, success criteria, high-level risks, assumptions and limitations for a project small enough to finish in six weeks, at work or in personal life, with quality built in from the start. This sample charters a twelve-person CPA firm's move from emailed tax documents to a secure client portal between December 1 and January 12, before the filing season. Its success criteria include measurable quality targets: complete document sets on first upload and zero misfiled client records.

CourseMGMT 645 Quality Management (MGMT645)
Module/Week2
AssignmentProject Charter and Proposal
Paper typeProject charter and proposal
Lengthabout 803 words, 3 double-spaced pages plus title page and references. Course guide: per the course guide, a project charter outlining the business case, project goals, success criteria, high-level risks, assumptions and limitations for a project that can be completed within six weeks, with quality concepts included from the beginning
FormatAPA 7 student paper
Points100
SchoolLiberty University Online
ProgramMS in Management and Leadership
Where it sitsModule/Week 2 in Liberty's published MGMT 645 course guide; current sections can differ
UpdatedOctober 2026

Free sample paper for MGMT 645 Week 2

1

Project Charter and Proposal: A Six-Week Secure Client Portal Rollout for a Twelve-Person CPA Firm Before Tax Season

 

[Student Name]

School of Business, Liberty University

MGMT 645: Quality Management

Project Charter and Proposal

[Instructor Name]

[Date]

 

The accounting firm, its staff and every figure are composites standing in for the project a student chooses; Rose's text, the PMBOK Guide and the study cited are real; the requirements follow Liberty's public course guide for MGMT 645.

2

Project Charter and Proposal: A Six-Week Secure Client Portal Rollout for a Twelve-Person CPA Firm Before Tax Season

Project Information

Why this part earns its pointsThe charter begins with the authorization and dates, which is what makes it a charter rather than a proposal alone.
3

Project title: Secure Client Portal Rollout. Sponsor: the firm's managing partner. Project manager: the firm's operations manager. Start date: December 1. Completion date: January 12, one week before the firm begins preparing returns. Budget: $14,500, covering the first year of portal software licenses for twelve users, setup and data migration support from the vendor, and staff time for training and client outreach. By approving this charter, the managing partner authorizes the project manager to use firm staff time and the approved budget to complete the project described below.

Business Case

The firm prepares about 1,150 individual and 140 business tax returns each season. Last season, clients sent roughly 4,100 documents by email, often as phone photographs, and staff saved them by hand into client folders. Three problems followed. First, about 24 percent of returns stalled at least once while staff waited for a missing form, and the average stalled return waited nine days. Second, two documents were saved to the wrong client's folder, and one of them was sent to the wrong client in a document request, which required a notification to the affected client. Third, emailing tax documents exposes clients' Social Security numbers and income information to interception, a risk the firm's insurer has asked it to reduce.

A secure portal addresses all three. Clients upload documents directly into their own encrypted folder, the portal shows each client a checklist based on last year's return so missing forms are visible before the client finishes, and staff no longer save attachments by hand. The firm expects to reduce stalled returns, eliminate misfiled documents and meet its insurer's request before renewal.

Project Goals

The project has three goals. First, configure and launch the portal with a folder for every active client, a document checklist for each client type and secure messaging enabled. Second, invite every active client, about 1,050 households and businesses, and provide simple instructions, a short video and phone help for those who need it. Third, train all twelve staff members to receive, review and file documents through the portal, and retire the practice of accepting tax documents by email.

Success Criteria

Why this part earns its pointsThe success criteria include quality targets with numbers, which brings quality into the project from the first document, as the guide requires.
4

The project will be judged successful if, by January 12, the portal is live with all active client folders created; at least 80 percent of active clients have logged in at least once; all twelve staff have completed training and processed a test client; and the firm has stopped accepting documents by email except through a documented exception. Two quality criteria will be measured during the first four weeks of the filing season: at least 85 percent of clients' document sets complete on first upload, measured against each client's checklist, and zero documents filed to the wrong client.

High-Level Risks

RiskPossible effectInitial response
Older clients struggle to use the portalLow adoption; documents still arrive by mail or emailPhone help line, printed guide, office drop-off scanning
Staff continue accepting email attachmentsOld errors persist; security risk remainsPartner announcement; email auto-reply pointing to portal
Client checklists built from incomplete prior-year dataClients upload the wrong documentsStaff review checklists for business clients before invitation
Vendor setup delayed by year-end demandLaunch slips into filing seasonSign contract by December 1; weekly vendor check-in
Holiday schedules reduce staff timeTraining incomplete by January 12Training sessions scheduled before December 20

Assumptions

The project assumes that the portal vendor can complete setup and migration within two weeks of contract signing, that client contact information in the practice management system is current for most clients, that staff can give about two hours a week each to training and testing in December, and that most clients have an email address and a smartphone or computer.

Limitations

The project cannot move its completion date, because the filing season begins on schedule. Its budget is fixed at $14,500. It will not change the firm's tax software, its billing system or its engagement letters, and it does not include building a paperless archive of prior years' records, which the partners have deferred to the summer.

Project Team

The operations manager leads the project. The firm's office administrator manages client invitations and the help line. A senior accountant builds and checks the document checklists. The vendor's implementation specialist configures the portal and migrates client data. The managing partner, as sponsor, approves changes and announces the new policy to clients.

Milestone Summary

WeekMilestone
1 (Dec 1-5)Contract signed; portal configuration begins; client data exported
2 (Dec 8-12)Client folders and checklists built; staff training session 1
3 (Dec 15-19)Pilot with 30 clients; checklist corrections; training session 2
4 (Dec 22-Jan 2)Invitations to all clients in two waves; help line opens
5 (Jan 5-9)Follow-up calls to clients who have not logged in; email policy takes effect
6 (Jan 12)Launch review; handoff to filing season operations

Quality From the Beginning

Why this part earns its pointsThe closing section shows quality planned into the charter itself, the requirement that sets MGMT 645's charter apart.
5

Rose (2014) argues that quality in projects is achieved mainly through planning and prevention rather than inspection at the end. This charter applies that idea in three ways. It defines the project's two most important defects, an incomplete document set and a misfiled document, before any work begins. It builds prevention into the product itself, since the checklist shows clients what is missing and the portal files each document into the right folder automatically. And it plans a pilot with 30 clients in week three, so problems are found while they are still cheap to fix. The PMBOK Guide places quality planning alongside scope and schedule planning rather than after them (Project Management Institute, 2017), and research on quality management supports the approach: in a survey of U.S. firms, Kaynak (2003) traced links from quality practices to operating results, some running straight through and some passing from one practice to another, which suggests that quality planned into the process pays off in results. For this firm, quality means a client's return is never held up by a document no one asked for, and no client ever receives another client's records.

6

References

Kaynak, H. (2003). The relationship between total quality management practices and their effects on firm performance. Journal of Operations Management, 21(4), 405-435. https://doi.org/10.1016/S0272-6963(03)00004-4

Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK guide) (6th ed.).

Rose, K. H. (2014). Project quality management: Why, what and how (2nd ed.). J. Ross Publishing.

What the MGMT 645 Week 2 instructions ask

Module/Week 2 of MGMT 645 brings the Project Charter and Proposal, worth 100 points, together with the 20-point Forum 1 reply, chapter 4 of the PMBOK Guide on integration, chapter 3 of Rose and a presentation. The guide describes the charter's contents directly: the business case, the goals of the project, the criteria for success, the high-level risks, and the assumptions and limitations. The project must be one that can be completed within six weeks, and it may come from the student's job or personal life. The guide also says quality concepts are to be included from the beginning. Every later assignment in the course, the full Project Management Plan, the Quality Improvement Plan and the closeout report, uses the same project, so the choice made here carries through four more papers.

How this MGMT 645 Week 2 example is built

The charter opens with project information and the sponsor's authorization, then states the business case: last tax season the firm received about 4,100 client documents by email, a quarter of returns stalled waiting for missing forms, and two documents were sent to the wrong client. It sets three goals, a working portal, every active client invited and trained, and a document checklist built into the upload process, with success criteria that include a quality target of 85 percent complete document sets on first upload. High-level risks, from staff resistance to clients who struggle with technology, appear in a table. Assumptions, limitations, the team and a milestone summary follow, and a section on quality explains how Rose's prevention focus shapes the project from its first week.

MGMT 645 Week 2 grading rubric: where the points go

The charter is graded on whether it includes every element the guide lists and on whether it describes a project that can really be finished in six weeks. Graders look for a business case grounded in the organization's own facts, goals that are specific, success criteria that are measurable and include quality measures, high-level risks that fit the project, and clearly separated assumptions and limitations. Because MGMT 645 is a quality course, the charter should show quality planning from the start, for instance by defining what a defect is for this project and how it will be prevented. A scope realistic for six weeks, clear organization under headings, and correct use of PMBOK Guide terms and Rose's concepts complete the evaluation.

MGMT 645 Week 2 help: mistakes that cost points

The most common problem is a project too large for six weeks, such as replacing an entire information system or building a facility. Choose a project with a clear start and finish that a small team can complete, and say why six weeks is enough. Another problem is success criteria that only restate the goals; write criteria someone could check, with numbers and dates. Include quality from the first page: define what a defect means for your project and set a target. Keep assumptions, things you believe to be true, separate from limitations, things you cannot change. Pick a project you can follow through four more assignments, since the plan, quality improvement plan and closeout all build on this charter.

Related MGMT 645 sample papers

Other MGMT 645 weeks

More MS in Management and Leadership sample papers

MGMT 645 Week 2 questions, answered

What is the MGMT 645 Project Charter and Proposal?

A 100-point Module/Week 2 assignment that sets out the business case, goals, success criteria, high-level risks, assumptions and limitations for a six-week project, with quality included from the start.

Where can I find a free MGMT 645 Week 2 sample paper?

This page presents a complete MGMT 645 Week 2 project charter for a CPA firm's six-week move from emailed tax documents to a secure client portal.

How long can the MGMT 645 project be?

The guide requires a project that can be completed within six weeks, chosen from the student's job or personal life, because the same project carries through the rest of the course.

What is the difference between an assumption and a limitation in a project charter?

An assumption is something the team treats as true without proof, such as staff availability; a limitation is a fixed boundary the project cannot change, such as a deadline or budget.

How do you include quality in a project charter?

Define what a defect means for the project, set measurable quality targets among the success criteria, and describe how errors will be prevented rather than found after the fact.

Use it as a model, or ask for your own

This paper is an original model written by our desk for study. It is not a submitted student paper and not an official Liberty University document. Read it for structure and reasoning, then write your own to the instructions in your Canvas course. If you want a version built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.