MGMT 645 Week 7 Project Closeout/Lessons Learned Example

Reviewed by Thomas Kerrigan, MBA, CPA · Liberty University · Updated

Here is a complete MGMT 645 Week 7 example of the Project Closeout and Lessons Learned report, the 200-point summary that finishes the course project in Liberty University MGMT 645, the quality management course of the MS in Project Management, prepared alongside PMBOK Guide chapters 5 to 7 and Rose's chapters 10 and 11. The guide asks for a summary of project completion for the same project used since the Week 2 charter. This sample closes out the accounting firm's move from emailed documents to its new portal. It reports results against every success criterion: the portal launched on January 12, 86 percent of clients logged in, and in the first four filing weeks 87 percent of submissions arrived complete the first time with no misfiled documents. It compares schedule and budget to baseline, records acceptance and handoff, and sets out six lessons, each with an owner.

CourseMGMT 645 Quality Management (MGMT645)
Module/Week7
AssignmentProject Closeout/Lessons Learned
Paper typeProject closeout report with lessons learned
Lengthabout 885 words, 3 double-spaced pages plus title page and references. Course guide: per the course guide, a summary of project completion, with lessons learned, for the same project used in the charter and proposal
FormatAPA 7 student paper
Points200
SchoolLiberty University Online
ProgramMS in Management and Leadership
Where it sitsModule/Week 7 in Liberty's published MGMT 645 course guide; current sections can differ
UpdatedOctober 2026

Free sample paper for MGMT 645 Week 7

1

Project Closeout and Lessons Learned: The CPA Firm's Secure Client Portal

 

[Student Name]

School of Business, Liberty University

MGMT 645: Quality Management

Project Closeout/Lessons Learned

[Instructor Name]

[Date]

 

The accounting firm, its results and every figure complete the composite project of this sample's Week 2 charter, Week 3 plan and Week 6 quality improvement plan; Rose's text, the PMBOK Guide and the study cited are real; the requirements follow Liberty's public course guide for MGMT 645.

2

Project Closeout and Lessons Learned: The CPA Firm's Secure Client Portal

Project Summary

Why this part earns its pointsThe summary states the outcome in the first paragraph, so a reader who stops there still knows whether the project succeeded.
3

The secure client portal launched on January 12, as scheduled, one week before the firm began preparing returns. Every active client received a portal folder and a checklist, all twelve staff completed training, and the firm stopped accepting tax documents by email on January 5, with a documented exception for clients who cannot use the portal. The project finished $320 under its $14,500 budget. Both quality criteria from the charter were met in the season's opening month.

Results Against Success Criteria

Success criterion (charter)TargetActualMet
Portal live with all active client foldersBy January 12January 12, 1,047 foldersYes
Clients logged in at least once80 percent by January 1286 percentYes
Staff trained and test client processedAll 12All 12 by December 19Yes
Email intake retired, exceptions documentedBy January 12January 5; 23 exceptionsYes
Document sets complete on first upload, first four weeks85 percent87 percentYes
Documents filed to the wrong clientZeroZeroYes

Schedule and Cost

The schedule held at every milestone except one. Building the business clients' checklists took three days longer than planned, because 31 business returns included forms the import did not recognize, and the senior accountant added them by hand. The operations manager chose to absorb the delay rather than shorten the pilot, judging that a smaller pilot would weaken the main quality check in the plan. The delay was absorbed by moving the second staff training session two days later, and the pilot started on time. The second pilot added by the Quality Improvement Plan used two days reserved for invitation corrections, and invitations went out on December 31 and January 2 as planned.

Cost itemBudgetActual
Portal licenses$6,600$6,600
Vendor setup and migration, including QIP changes$3,200$3,480
Client guide and video$700$640
Staff overtime$3,000$3,460
Reserve$1,000Not drawn
Total$14,500$14,180

Staff overtime ran $460 over its line because the help line received about 340 calls in the first two weeks of January, more than expected, mostly from clients over seventy. The vendor's added work on scan mode and the tax-year display cost $280. Both were covered within the total budget.

Quality Results

Why this part earns its pointsThe quality section reports against the metrics set earlier in the course and repeats the Pareto analysis, which shows continuous improvement rather than a one-time fix.
4

The first pilot reached 60 percent complete first uploads. After the improvements in the Quality Improvement Plan, the second pilot of 20 clients reached 81 percent, and the operations manager adopted the changes for all clients. In the first four weeks of the season, 87 percent of 612 submitted document sets were complete on first upload, above the 85 percent target, and no document was filed to the wrong client. A new Pareto count of the season's 104 defects showed a different leading problem: charitable donation receipts, missing from 31 sets, now ranked first, followed by missing brokerage statements at 22, which had fallen from the top position. Rose (2014) describes quality improvement as continuing rather than finished, and the firm will add a receipts reminder to the February 20 message as the next improvement.

Stakeholder Feedback

The firm asked for feedback from both clients and staff. A three-question survey sent to all clients after their first upload drew 412 responses: 81 percent said the portal was easier than email, 12 percent said it was about the same and 7 percent said it was harder, most of them clients over seventy. Several clients wrote that the checklist helped them see what they had forgotten. Staff feedback, gathered at the lessons-learned meeting, was more mixed. Preparers liked receiving complete sets and no longer saving attachments by hand, but two senior staff said the first weeks of help line calls took time away from returns. The managing partner noted that two long-time business clients who had threatened to leave over last year's delays renewed their engagements, and one referred a new client because of the portal.

These responses matter for quality as well as satisfaction. Rose (2014) treats the customer's judgment as the final measure of quality, and the client survey confirms what the completeness metric showed: the product works for most users and needs more support for a minority.

Acceptance and Handoff

The managing partner formally accepted the project on January 16 after reviewing the results table. Ownership of the portal passed to the office administrator, who now manages client access and the help line, and ownership of the checklists passed to the senior accountant, who will update them each December. The vendor's implementation contact was replaced by the firm's ordinary support channel. The PMBOK Guide treats the transfer of the product to operations and the archiving of project records as part of closing a project (Project Management Institute, 2017), and the firm's project folder now holds the charter, plan, quality improvement plan, change log and this report.

Lessons Learned

Why this part earns its pointsEach lesson names a cause and an owner, which turns the review into commitments rather than general advice.
5

Anbari et al. (2008) treat the review held at a project's end as a skill organizations must build on purpose, not a courtesy meeting. The team held a one-hour review on January 15 and recorded six lessons:

  • 1. Business checklists took longer to build than planned because the import missed uncommon forms; next December, the senior accountant will review business returns for unusual forms a week before the import.
  • 2. The pilot found problems that no one inside the firm had predicted; future client-facing changes will include a pilot of at least 25 clients, owned by the operations manager.
  • 3. Older clients needed more help than budgeted; next year the help line budget will be based on this year's call counts, and the office administrator will call clients over seventy before invitations go out.
  • 4. Checklist wording caused the largest defect; the senior accountant will test checklist wording with five clients each year before the season.
  • 5. The second pilot showed that small, fast tests of a change work; the operations manager will use the plan-do-check-act cycle for the receipts reminder.
  • 6. The fixed deadline kept decisions quick; future firm projects will set a firm end date in the charter.

The project met every criterion it set itself, and its most useful result may be a firm that now measures its own work.

6

References

Anbari, F. T., Carayannis, E. G., & Voetsch, R. J. (2008). Post-project reviews as a key project management competence. Technovation, 28(10), 633-643. https://doi.org/10.1016/j.technovation.2007.12.001

Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK guide) (6th ed.).

Rose, K. H. (2014). Project quality management: Why, what and how (2nd ed.). J. Ross Publishing.

What the MGMT 645 Week 7 instructions ask

Module/Week 7 of MGMT 645 grades only the closeout report, the final 200-point paper of the course, read with chapters 5 through 7 of the PMBOK Guide on scope, schedule and cost, chapters 10 and 11 of Rose and two presentations. The guide's instruction is short: using the same project presented in the charter and proposal, provide a summary of project completion. In practice that means reporting the outcome against the charter's goals and success criteria and the plan's baselines, documenting acceptance and the handoff to operations, and recording lessons learned. Because the course is about quality, the quality results deserve particular attention, measured against the targets set in the project management plan and the Quality Improvement Plan.

How this MGMT 645 Week 7 example is built

The report opens with a summary of what was delivered and when. A results table compares each charter success criterion with its actual value, from client logins to the two quality metrics. Schedule and budget sections explain a three-day slip in checklist building, recovered before launch, and a final cost of $14,180 against the $14,500 budget. A quality section reports the second pilot's improvement to 81 percent complete first uploads and the season's first four weeks at 87 percent, with the remaining defects ranked by a fresh Pareto count. Acceptance by the managing partner and the handoff of the help line to the office administrator follow. Six lessons learned, each stating an event, its cause and the fix, close the report with owners.

MGMT 645 Week 7 grading rubric: where the points go

The closeout report is graded on whether it gives a complete and honest summary of the project's completion, for the same project used throughout the course. Graders look for results reported against the charter's goals and success criteria with real figures, comparisons of schedule and cost with the plan's baselines, an account of quality results against the quality targets, formal acceptance and handoff, and lessons learned that are specific and actionable. Honest reporting of what went wrong, as well as what went right, shows mature project management. Connections to the PMBOK Guide's closing processes and to Rose's treatment of quality and continuous improvement, clear tables and headings, and current APA style complete the evaluation.

MGMT 645 Week 7 help: mistakes that cost points

The most common weakness in closeout reports is a narrative of the project's activities with no comparison to what was planned. Build the report around the charter's success criteria and the plan's baselines, criterion by criterion, so the reader can see what was achieved. Report shortfalls plainly and explain them. For lessons learned, avoid general statements such as communicate more; state each lesson as an event, its cause and the change it calls for, and name who will carry it forward. Include the handoff, since a project is not closed until its product belongs to the people who will run it. Keep the quality section close to the metrics defined earlier in the course.

Related MGMT 645 sample papers

Other MGMT 645 weeks

More MS in Management and Leadership sample papers

MGMT 645 Week 7 questions, answered

What is the MGMT 645 Project Closeout/Lessons Learned assignment?

The 200-point Module/Week 7 report summarizing the completion of the same project used since the Week 2 charter, including results, acceptance and lessons learned.

Where can I find a free MGMT 645 Week 7 sample paper?

A finished MGMT 645 Week 7 closeout and lessons learned report for a CPA firm's secure client portal rollout is published on this page.

What should a project closeout report include?

Results against the charter's success criteria, final schedule and cost compared with baselines, quality results, formal acceptance, the handoff to operations and specific lessons learned.

How should lessons learned be written?

As concrete accounts of an event, its cause and the different practice it calls for next time, each with an owner, rather than general advice.

What comes after the MGMT 645 closeout report?

The 150-point Integration of Faith and Learning assignment in Module/Week 8, which applies a Christian worldview to managing projects, especially quality planning, assurance and control.

Use it as a model, or ask for your own

This paper is an original model written by our desk for study. It is not a submitted student paper and not an official Liberty University document. Read it for structure and reasoning, then write your own to the instructions in your Canvas course. If you want a version built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.