BUSI 415 Week 4 Project: Communication Plan Example

Reviewed by Thomas Kerrigan, MBA, CPA · Liberty University · Updated

This BUSI 415 Week 4 sample is the communication plan for the same composite recreation center project used in the Week 2 resource plan. Following the PMBOK Guide's Plan Communications Management process, it analyzes the stakeholders' information needs, counts the communication channels the team must manage, assigns push, pull and interactive methods, and lays out a communication matrix covering who receives what, how often, in what form and from whom. It adds an escalation path, meeting rules, a public information approach for residents and a way to check that messages were understood. Research tying a project manager's listening and message skills to team satisfaction and productivity shapes the plan, and Proverbs on answering before hearing supplies the biblical integration. The plan is worth 150 points in Liberty University BUSI 415, one of four linked projects BS in Business Administration students build on a single scenario.

CourseBUSI 415 Advanced Project Management (BUSI415)
Module/Week4
AssignmentProject: Communication Plan
Paper typeProject communications management plan
Lengthabout 1,027 words, 4 double-spaced pages plus title page and references. Course guide: a project plan following current PMBOK guidelines, with 1 biblical integration, the course textbook and at least 1 scholarly article, in current APA format
FormatAPA 7 student paper
Points150
SchoolLiberty University Online
ProgramBS in Business Administration
Where it sitsModule/Week 4 in Liberty's published BUSI 415 course guide; current sections can differ
UpdatedOctober 2026

Free sample paper for BUSI 415 Week 4

1

Communications Management Plan: Fairmont Hills Community Recreation Center

 

[Student Name]

School of Business, Liberty University

BUSI 415: Advanced Project Management

Project: Communication Plan

[Instructor Name]

[Date]

 

The city, the project and its stakeholders are composites standing in for the instructor's scenario; the PMBOK Guide, the handbook and the research cited are real.

Why this part earns its pointsThe opening ties the plan to the PMBOK process and to the resource plan, so the reader sees one project, not four papers.
2

Communications Management Plan: Fairmont Hills Community Recreation Center

Purpose and Scope

This plan describes how information about the Fairmont Hills Community Recreation Center project will be planned, distributed, monitored and updated over the project's fourteen months. It follows the PMBOK Guide's Plan Communications Management process (Project Management Institute, 2013) and uses the roles defined in the project's resource management plan. Dinsmore and Cabanis-Brewin (2014) describe communication as the means by which a project manager integrates the work of people who do not report to the project, which is the situation of a city project staffed from five departments with an outside contractor. The plan covers internal team communication, reporting to the sponsor and council, coordination with the general contractor and information for residents.

Three constraints shape it. First, the city's open records law means that project email and reports may be requested by the public, so status reports are written to be accurate and courteous even when they describe problems. Second, five of the eight city roles are part-time, so the plan cannot assume people will read long messages; reports are limited to two pages, and decisions are made in meetings rather than by email chains. Third, the council meets on fixed dates, so any decision that needs a vote must be prepared at least three weeks ahead, and the sponsor's updates are scheduled around the council calendar.

Communication Technology

The project uses the city's existing tools rather than adding new ones, because Dinsmore and Cabanis-Brewin (2014) caution that unfamiliar technology adds a learning burden at the start of a project, when the team has the least time. The project site on the city intranet holds all reference documents, with a single folder structure that mirrors the work breakdown structure. Email is used for notices and records, not for decisions. The contractor's daily reports and photographs are uploaded to a shared folder that the construction manager reviews each morning. Video calls are used for the weekly coordination meeting when site work keeps the construction manager away from city hall, and every meeting has a call-in option so that part-time members can attend from their own departments.

Stakeholder Communication Requirements

The table below lists the project's stakeholders and what each needs from the project.

StakeholderInterestInformation neededInfluence
City councilApproves budget changes, answers to residentsBudget and schedule status, major risks, decisions requiring a voteHigh
Sponsor and steering committeeOwns the outcomeProgress against baseline, issues needing a decision, change requestsHigh
Project teamDoes the workSchedule, assignments, design changes, decisionsMedium
Functional managersLend staffStaff time needed, release datesMedium
General contractorBuilds the centerApprovals, inspections, payment status, design clarificationsMedium
Residents and user groupsWill use the centerOpening date, programs, construction disruptionsMedium
Neighbors of the siteLive with the workHours, traffic, noise, road closuresLow to medium

The eight city roles in the resource plan, the contractor's project manager and superintendent, and two council liaisons make twelve people who exchange information regularly. Using the PMBOK Guide's formula of n(n-1)/2, those twelve people have 66 potential communication channels. No project manager can personally maintain 66 channels, so the plan assigns owners for each flow of information and uses pull methods for routine reference material.

Why this part earns its pointsThe methods section applies push, pull and interactive communication to specific audiences, as the PMBOK Guide describes.
3

Communication Methods

The Project Management Institute (2013) distinguishes three methods. Push communication, such as reports and email, is used for records that must be sent and kept. Pull communication, a project site on the city's intranet, holds the schedule, drawings, meeting minutes, the change log and the risk register, so that team members can retrieve current information without asking. Interactive communication, in meetings and walk-throughs, is used whenever people must make a decision or change how they work.

The plan relies on interactive methods more than many city projects do, for a reason supported by research. Henderson (2008) found that a project manager's competence in decoding messages, listening and confirming understanding, along with encoding clear messages, was related to team members' satisfaction and productivity. A report that arrives on time but is misunderstood has not communicated anything, so every decision meeting in this plan ends with a confirmation step. The person most affected by each decision states what it means for their work before the meeting moves on.

Communication Matrix

CommunicationPurposeAudienceMethodFrequencyOwner
Team coordination meetingReview the coming two weeks, resolve conflictsProject teamInteractive, 30 minutesWeekly, TuesdayProject manager
Contractor progress meetingSchedule, inspections, requests for informationConstruction manager, contractor, project managerInteractive, on siteWeekly, ThursdayConstruction manager
Status reportProgress, cost, schedule, top risksSponsor, steering committeePush, two pagesBiweeklyProject manager
Cost reportSpending against budget, forecastSponsor, finance directorPushMonthlyFinance analyst
Steering committee meetingApprove changes above $25,000, settle staffing conflictsSponsor, department directorsInteractiveMonthlySponsor
Council updateStatus, decisions neededCity councilPush memo and presentationQuarterlySponsor
Project siteCurrent schedule, drawings, minutes, change logTeam, functional managersPullUpdated weeklyProject manager
Neighbor noticeWork hours, closuresResidents near the sitePush, mailed and postedTwo weeks before disruptionsCommunications officer
Community page and newsletterProgress, opening programsResidents, user groupsPull and pushMonthlyCommunications officer
Why this part earns its pointsThe escalation path reuses the decision thresholds from the resource plan, so the two documents agree.
4

Escalation Path

Issues are resolved at the lowest level that has authority. A team member raises an issue at the weekly coordination meeting or, if urgent, directly with the project manager. The project manager resolves issues within the approved baseline and any change below $25,000. Issues that affect another department's staff, or changes above $25,000, go to the steering committee, and the sponsor may call a special meeting within three working days. Changes to the total budget or the opening date go to the city council. Every escalated issue is entered in the issue log on the project site with an owner and a due date.

Meeting Rules

Meetings start on time, have a written agenda circulated a day ahead, and end with decisions and action items read back aloud. Minutes are posted to the project site within one working day. The weekly coordination meeting is limited to thirty minutes; topics needing more time are taken to a separate working session with only the people concerned.

Communicating With Residents

Residents have no formal role in the project but strong influence, since they speak to council members. The communications officer will hold two public information sessions, one before construction and one before opening, and will answer questions submitted through the city's website within five working days. Disruptive work, such as a road closure for utility connections, will be announced at least two weeks ahead.

Biblical Integration

Proverbs warns that the person who answers before the matter has been heard out ends in folly and disgrace (English Standard Version Bible, 2001/2016, Proverbs 18:13). The plan applies that warning in two places. The confirmation step in meetings requires the project manager to hear how a decision is understood before treating it as communicated, and the public sessions are scheduled before construction begins, so residents' concerns can still shape traffic and noise plans rather than being answered after the fact.

Updating the Plan

The project manager will review this plan at each phase gate and whenever a stakeholder is added or a communication proves ineffective, recording changes in the change log. Its effectiveness will be checked through a three-question survey of team members and steering committee members at the end of Months 3, 8 and 13. The survey asks whether people received the information they needed, whether it arrived in time to act on, and whether any meeting or report could be dropped. Results are reported to the steering committee, and the plan is revised within two weeks of each survey. If a stakeholder group repeatedly reports surprises, the project manager will add an interactive method for that group, following the plan's principle that information has been communicated only when it has been understood.

5

References

Dinsmore, P. C., & Cabanis-Brewin, J. (Eds.). (2014). The AMA handbook of project management (4th ed.). AMACOM.

English Standard Version Bible. (2016). Crossway. (Original work published 2001)

Henderson, L. S. (2008). The impact of project managers' communication competencies: Validation and extension of a research model for virtuality, satisfaction, and productivity on project teams. Project Management Journal, 39(2), 48-59. https://doi.org/10.1002/pmj.20044

Project Management Institute. (2013). A guide to the project management body of knowledge (PMBOK guide) (5th ed.). Project Management Institute.

What the BUSI 415 Week 4 instructions ask

Week 4 assigns chapter 10 of the PMBOK Guide, on communications management, with a presentation, and it brings the Forum 2 replies, two of 250 to 350 words, along with this second project assignment, worth 150 points. Like every project part, the communication plan answers the instructor's scenario, follows current PMBOK guidelines, draws on the assigned textbook and one or more peer-reviewed studies, and applies a principle from Scripture, all cited in APA style. Under the fifth edition the course lists, the plan is the main output of Plan Communications Management, and it should describe stakeholder communication requirements, the information to be shared, methods, frequency, responsibilities, escalation and how the plan itself will be updated.

How this BUSI 415 Week 4 example is built

The sample starts from the stakeholders, not the channels: a short register lists each group and what it needs to know, and a calculation of the number of communication channels shows why the project manager cannot be the hub for everything. A communication matrix then assigns each report or meeting an owner, audience, method and frequency. Separate sections set the escalation path, rules for meetings and a plan for residents, who are stakeholders with no formal role but real influence. Henderson's research on communication competence justifies the plan's confirmation step, in which recipients say what a change means for them. The biblical integration from Proverbs closes the plan before a brief conclusion.

BUSI 415 Week 4 grading rubric: where the points go

The communication plan is graded on whether it applies the PMBOK Guide's communications planning to the scenario, covers the plan's expected contents, uses the course textbook and at least one scholarly article accurately, and includes a meaningful biblical integration, all in current APA format. Instructors expect a communication requirements analysis that starts from stakeholders' needs, a clear assignment of methods and responsibilities, and a realistic schedule of reports and meetings. A matrix or table is close to essential, since the plan has to be usable at a glance. Consistency with the resource plan from Week 2, such as the same roles and names, also signals careful work.

BUSI 415 Week 4 help: mistakes that cost points

List every stakeholder before choosing any channel, and write down what each needs to know and why. Use the channel formula to show the complexity, then design around it with owners for each flow of information. Keep the matrix specific: a named owner, a day of the week and a format, not "as needed." Include at least one interactive method for any audience that must act on information. Plan for people outside the organization, such as residents or customers, since the instructor's scenario usually has some. Reuse the roles from your resource plan exactly, and keep a running list of risks you notice while writing, because the risk register in Week 6 will need them.

Related BUSI 415 sample papers

Other BUSI 415 weeks

More BS in Business Administration sample papers

BUSI 415 Week 4 questions, answered

What is the BUSI 415 Communication Plan?

The second BUSI 415 project, worth 150 points in Module/Week 4: a PMBOK-based plan for the instructor's scenario setting out who needs what information, by which method, how often and from whom.

Where can I find a free BUSI 415 Week 4 sample paper?

This page presents a full BUSI 415 Week 4 communication plan for a composite recreation center, with a stakeholder needs table, a channel count, a communication matrix and an escalation path.

What goes in a communications management plan?

Stakeholder communication requirements, the information to be distributed, methods and technology, frequency, the person responsible for each communication, escalation procedures, a glossary where needed and how the plan will be updated.

What is a communication requirements analysis?

The PMBOK Guide's technique for determining what information each stakeholder needs, combining the number of stakeholders and channels with each group's role, location and interest in the project.

What else is due in BUSI 415 Module/Week 4?

Replies to two Forum 2 threads, each between 250 and 350 words, add 50 points; the reading is the PMBOK Guide's tenth chapter, on communications, plus a presentation.

Use it as a model, or ask for your own

This paper is an original model written by our desk for study. It is not a submitted student paper and not an official Liberty University document. Read it for structure and reasoning, then write your own to the instructions in your Canvas course. If you want a version built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.