BUSI 415 Week 2 Project: Resource Management Plan Example

Reviewed by Thomas Kerrigan, MBA, CPA · Liberty University · Updated

This BUSI 415 Week 2 sample is the first of the course's four project assignments, a resource management plan for a composite city building a $6.8 million community recreation center over fourteen months. Built on the PMBOK Guide's human resource planning outputs, it sets out roles and responsibilities in a RACI chart, the project's reporting structure, a staffing plan covering how city staff and contractors are acquired, scheduled and released, training needs, recognition and team development, and safety and compliance. Research linking human resource practices to project success, and Tuckman's model of how teams develop, support the choices. Jethro's advice to Moses to share the load supplies the biblical integration. Liberty University BUSI 415 weighs the plan at 150 points, the same as each later part, and BS in Business Administration students keep the scenario through Week 8.

CourseBUSI 415 Advanced Project Management (BUSI415)
Module/Week2
AssignmentProject: Resource Management Plan
Paper typeProject resource management plan
Lengthabout 1,103 words, 4 double-spaced pages plus title page and references. Course guide: a project plan following current PMBOK guidelines, with 1 biblical integration, the course textbook and at least 1 scholarly article, in current APA format
FormatAPA 7 student paper
Points150
SchoolLiberty University Online
ProgramBS in Business Administration
Where it sitsModule/Week 2 in Liberty's published BUSI 415 course guide; current sections can differ
UpdatedOctober 2026

Free sample paper for BUSI 415 Week 2

1

Resource Management Plan: Fairmont Hills Community Recreation Center

 

[Student Name]

School of Business, Liberty University

BUSI 415: Advanced Project Management

Project: Resource Management Plan

[Instructor Name]

[Date]

 

The city, the project and its staff are composites standing in for the instructor's scenario; the PMBOK Guide, the handbook and the research cited are real.

Why this part earns its pointsThe summary fixes the scenario's numbers so every later plan can stay consistent with them.
2

Resource Management Plan: Fairmont Hills Community Recreation Center

Project Summary

The City of Fairmont Hills will build a 32,000-square-foot community recreation center with a gymnasium, a fitness area, three multipurpose rooms and a teaching kitchen. Council has approved $6.8 million for the work and expects the doors to open fourteen months after design approval. The city's Parks and Recreation Department sponsors the project; design is complete, and construction will be performed under contract by a general contractor selected through the city's sealed-bid process. The project manager, Jordan Ellis, is a city employee assigned full time from the Public Works Department.

This plan follows the process the PMBOK Guide calls Plan Human Resource Management (Project Management Institute, 2013), whose output, the human resource management plan, defines how project roles are identified, staffed, managed and eventually released. Dinsmore and Cabanis-Brewin (2014) stress that this planning matters most in organizations where the project manager borrows people from functional departments, which is the city's situation. Equipment and materials are covered in the procurement management plan; this plan covers people.

Roles and Responsibilities

The project requires the roles below. City staff remain employees of their home departments and are assigned to the project for a defined share of their time.

RoleFilled byTime on projectMain responsibilities
Project sponsorDirector of Parks and Recreation5 percentApproves the charter and major changes, chairs the steering committee, resolves conflicts with other departments
Project managerJordan Ellis, Public Works100 percentPlans and controls the project, leads the team, reports to the sponsor and council
Construction managerSenior engineer, Public Works60 percentOversees the contractor, inspects work, reviews pay applications
Procurement officerPurchasing Division25 percentRuns bids, drafts contracts, manages contract changes
Finance analystFinance Department20 percentTracks costs, processes payments, reports against budget
Program coordinatorParks and Recreation40 percentDefines program space needs, plans opening programs, trains staff
IT specialistInformation Technology15 percentNetwork, security cameras, registration and access systems
Communications officerCity Manager's Office10 percentPublic notices, council updates, opening event

The RACI chart below assigns the major deliverables. In each row, R marks the people doing the work, A the single person answerable for it, C those whose advice is sought and I those kept up to date.

DeliverableSponsorProject managerConstruction managerProcurement officerFinance analystProgram coordinator
Construction contract awardARCRCI
Building constructionIARCIC
Monthly cost reportIACIRI
Furniture and equipmentIACRCC
Opening programs and staffingCAIIIR

Each row has a single accountable person, so no decision can fall between two departments. The chart also exposes overload early: the project manager is accountable for four of the five deliverables, which is why the construction manager and procurement officer carry the doing of most of them. If a row ever shows two As, the steering committee will settle which department owns the outcome before the work begins, rather than in the middle of a dispute.

Project Organization

The project uses a balanced matrix. Team members report to the project manager for project work and to their functional managers for performance reviews, pay and their other duties. The project manager reports to the sponsor, who chairs a steering committee with the directors of Public Works, Finance and Information Technology. A balanced matrix was chosen over a dedicated project team because the city builds a major facility only every few years; hiring full-time project staff would leave them idle afterward, while borrowing staff keeps their knowledge in the departments that will run and maintain the building. The steering committee meets monthly to approve changes above $25,000 and to settle disputes over staff time. The general contractor reports to the construction manager under the terms of its contract and is not part of the city's team structure.

Why this part earns its pointsThe staffing section answers the three PMBOK questions: how people arrive, when they are needed and how they leave.
3

Staffing Management Plan

Staff Acquisition

Each city role is filled by negotiation with the functional manager concerned, confirmed in a written assignment memo signed by the sponsor that states the percentage of time, the start and end dates and the person's backup. Dinsmore and Cabanis-Brewin (2014) note that such agreements protect the project when departmental priorities shift. No new hires are planned; if the IT specialist's time proves insufficient during systems installation, the city's existing contract with a network vendor will be used.

Resource Calendar

Staffing rises and falls with the project's phases.

PhaseMonthsPeak city staffNotes
Contract award1 to 24Procurement officer at 50 percent during bidding
Site work and structure3 to 75Construction manager at full time during foundations
Interior and systems8 to 127IT specialist at 40 percent for cabling and access control
Fit-out and opening13 to 148Program coordinator at full time; front desk staff trained

Staff Release

Each person returns to their department when their deliverables are accepted. The procurement officer's assignment drops to 10 percent after contract award, and the construction manager is released after the final inspection and punch list. Releasing people on a known date, announced a month ahead, keeps functional managers willing to lend staff for the next project.

Training Needs

Three training needs are planned. The construction manager and the project manager will complete the city's contract administration course before the contract is awarded. Team members who have not used the city's project management software will receive a two-hour session in Month 1. In Month 13, the program coordinator will train front desk and fitness staff on the registration system and the building's emergency procedures, using vendor materials.

Why this part earns its pointsThe development plan applies Tuckman's stages and the research on human resource practices to the city's matrix.
4

Recognition, Rewards and Team Development

Because the project manager does not control pay, recognition must work through the people who do. At each phase gate, the project manager will send a short note to each member's functional manager describing that person's contributions, and the sponsor will recognize the team at a city council meeting at substantial completion.

Development is planned rather than left to chance. Tuckman (1965) found that new groups pass through forming, storming, norming and performing, and the plan responds to each: a kickoff workshop in Month 1 sets ground rules and decision rights; a facilitated session after the first monthly report addresses disagreements before they harden; weekly coordination meetings, kept to thirty minutes, establish norms; and from Month 4 the team runs its own progress reviews. Belout and Gauvreau (2004) studied the effect of human resource management on project success and found that its influence was weaker than expected and depended on the project's structure and phase. That finding argues for targeted practices at the points where people matter most, such as the move from construction to opening, rather than for programs the team has no time to use.

Compliance and Safety

City personnel policies apply to all team members, including overtime rules for hourly staff during the opening month. All staff entering the site must complete the contractor's site safety orientation and wear the required protective equipment; the construction manager will keep a log of orientations. The general contractor is responsible for its own workers' safety under its contract, and the project manager will review the contractor's safety reports monthly.

Biblical Integration

Exodus records Moses sitting from morning to evening to settle the people's cases alone, until Jethro, his father-in-law, told him he would wear himself out and urged him to put trustworthy, capable people in charge of layered groups of the people, so that ordinary disputes were settled below him and only the hard ones reached him (English Standard Version Bible, 2001/2016, Exodus 18:13-26). The principle shapes this plan in two ways. Decision rights are delegated in writing, with a $25,000 threshold below which the project manager decides and above which the steering committee does, so that the project manager is not a bottleneck. And each person is chosen for capability and character, which is why the plan asks functional managers to assign people by name rather than send whoever is available.

Conclusion

This plan identifies the roles the recreation center needs, assigns each deliverable to one accountable person, sets out how city staff will be obtained, scheduled, trained, recognized and released, and plans the team's development through its early stages. The project manager will revise it at every phase gate, and the communication, risk and procurement plans that follow are built on its roles.

5

References

Belout, A., & Gauvreau, C. (2004). Factors influencing project success: The impact of human resource management. International Journal of Project Management, 22(1), 1-11. https://doi.org/10.1016/S0263-7863(03)00003-6

Dinsmore, P. C., & Cabanis-Brewin, J. (Eds.). (2014). The AMA handbook of project management (4th ed.). AMACOM.

English Standard Version Bible. (2016). Crossway. (Original work published 2001)

Project Management Institute. (2013). A guide to the project management body of knowledge (PMBOK guide) (5th ed.). Project Management Institute.

Tuckman, B. W. (1965). Developmental sequence in small groups. Psychological Bulletin, 63(6), 384-399. https://doi.org/10.1037/h0022100

What the BUSI 415 Week 2 instructions ask

Week 2 assigns chapter 17 of Dinsmore and Cabanis-Brewin and chapter 13 of the PMBOK Guide, on stakeholders, with a presentation; besides this 150-point project, students owe the Forum 1 replies, worth 50. All four projects answer a single instructor-written scenario; for this first one, the plan has to follow current PMBOK practice and draw on the textbook, at least one research article and a biblical principle, with APA citations throughout. The PMBOK Guide's fifth edition, the edition the course schedule lists, calls this document the human resource management plan; later editions widened it to cover physical resources as well, which is why the course names it a resource management plan.

How this BUSI 415 Week 2 example is built

The sample reads like a working project document. A short scenario summary comes first, then roles and responsibilities with a RACI chart for the major deliverables, so each decision has exactly one accountable person. The reporting structure explains the matrix arrangement with city departments. The staffing plan covers acquisition, a resource calendar by phase and the release of people as their work ends, followed by training, recognition and a team development plan built on Tuckman's stages. A compliance and safety section and the biblical integration close the plan. Research on human resource practices in projects justifies spending effort on team development rather than treating staffing as clerical work.

BUSI 415 Week 2 grading rubric: where the points go

Project assignments in BUSI 415 are graded on whether they follow current PMBOK guidance for the plan in question, apply it to the instructor's scenario rather than describing it in general, and meet the source requirements: the course textbook, at least one scholarly research article and one biblical integration, cited in current APA format. Instructors look for the plan's standard parts, here roles and responsibilities, organization charts and a staffing management plan with acquisition, calendars, release, training, recognition, compliance and safety. Tables help, since a RACI chart communicates in seconds what a paragraph cannot. A plan that would actually let a team start work scores best.

BUSI 415 Week 2 help: mistakes that cost points

Read the instructor's scenario twice and list every role it implies before writing anything. Build the RACI chart early, and check that each row has exactly one A. Use PMBOK terms exactly, because the grader will look for staffing management plan, resource calendar and release criteria by name. Tie the scholarly article to a decision in the plan rather than summarizing it in its own section. Keep the biblical integration practical: a principle that changes who does what, or how people are treated. Save the scenario details you invent, such as names and budgets, in a separate file, because the communication, risk and procurement plans in Weeks 4, 6 and 8 must stay consistent with them.

Related BUSI 415 sample papers

Other BUSI 415 weeks

More BS in Business Administration sample papers

BUSI 415 Week 2 questions, answered

What is the BUSI 415 Resource Management Plan?

BUSI 415's opening project, 150 points in Week 2: a plan, built on PMBOK practice, for staffing the instructor's scenario, drawing on the textbook, a journal article and Scripture.

Where can I find a free BUSI 415 Week 2 sample paper?

This page holds a complete BUSI 415 Week 2 resource management plan for a composite city recreation center, with a RACI chart, staffing plan, resource calendar and team development plan.

What goes in a project resource management plan?

Roles and responsibilities, the project organization chart and a staffing management plan covering acquisition, resource calendars, release, training, recognition and rewards, compliance and safety, following the PMBOK Guide.

What is a RACI chart?

A grid of deliverables against people in which each cell carries a letter: R for doing the task, A for owning the result, C for giving input beforehand and I for receiving news afterward.

What else is due in BUSI 415 Module/Week 2?

Students also answer two classmates' Forum 1 threads in 250 to 350 words each, for 50 points, while reading the handbook's chapter 17 and the PMBOK Guide's chapter 13 on stakeholders.

Use it as a model, or ask for your own

This paper is an original model written by our desk for study. It is not a submitted student paper and not an official Liberty University document. Read it for structure and reasoning, then write your own to the instructions in your Canvas course. If you want a version built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.