BUSI 415 Week 6 Project: Risk Register and Risk Management Plan Example

Reviewed by Thomas Kerrigan, MBA, CPA · Liberty University · Updated

This BUSI 415 Week 6 sample is the third project assignment for the composite recreation center scenario: a risk management plan followed by a risk register. The plan defines the method, roles, budget and timing for risk work, the risk categories, scales for probability and impact, a probability and impact matrix, and how risks will be tracked. The register then analyzes ten threats and one opportunity, from bad soil to steel prices and a slow permit, each with a cause, a score, a response strategy, an owner and a trigger, and an expected monetary value calculation sizes the contingency reserve. Research on project managers who avoid uncomfortable risks shapes the plan's review rules. Proverbs on the prudent person who sees danger supplies the Scripture. Liberty University BUSI 415 grades register and plan together at 150 points; BS in Business Administration students carry the scenario into Week 8.

CourseBUSI 415 Advanced Project Management (BUSI415)
Module/Week6
AssignmentProject: Risk Register and Risk Management Plan
Paper typeRisk management plan and risk register
Lengthabout 1,019 words, 4 double-spaced pages plus title page and references. Course guide: a project plan and register following current PMBOK guidelines, with 1 biblical integration, the course textbook and at least 1 scholarly article, in current APA format
FormatAPA 7 student paper
Points150
SchoolLiberty University Online
ProgramBS in Business Administration
Where it sitsModule/Week 6 in Liberty's published BUSI 415 course guide; current sections can differ
UpdatedOctober 2026

Free sample paper for BUSI 415 Week 6

1

Risk Management Plan and Risk Register: Fairmont Hills Community Recreation Center

 

[Student Name]

School of Business, Liberty University

BUSI 415: Advanced Project Management

Project: Risk Register and Risk Management Plan

[Instructor Name]

[Date]

 

The city, the project and its risks are composites standing in for the instructor's scenario; the PMBOK Guide, the handbook and the research cited are real, and the probabilities and costs are illustrative.

Why this part earns its pointsThe plan sets the method, roles and scales first, because a register scored without defined scales cannot be compared.
2

Risk Management Plan and Risk Register: Fairmont Hills Community Recreation Center

Part 1: Risk Management Plan

Methodology

Risk management for the Fairmont Hills Community Recreation Center follows the risk processes of the PMBOK Guide (Project Management Institute, 2013): plan risk management, identify risks, perform qualitative and, for the largest risks, quantitative analysis, plan responses, and control risks. Risks are identified through a workshop with the project team and the general contractor at contract award, through the assumptions in the resource and communication plans, and through a checklist drawn from the city's two previous building projects. Dinsmore and Cabanis-Brewin (2014) recommend combining several identification techniques because each catches risks the others miss.

Roles and Responsibilities

The project manager owns this plan and the register. Each risk has a named risk owner who monitors its trigger and carries out the response. The construction manager leads identification of site and construction risks; the finance analyst maintains the contingency log. The steering committee approves use of the contingency reserve above $25,000 and reviews the top five risks monthly.

Budget and Timing

A contingency reserve of $420,000, about 6 percent of the budget, is held for identified risks, based on the expected monetary value analysis below. A management reserve of $200,000 is held by the sponsor for unknown risks. Risks are reviewed at every weekly coordination meeting for the top five and in full at each monthly steering committee meeting and each phase gate.

Research supports a firm review rule. Kutsch and Hall (2010) studied IT project managers and found that many deliberately ignored certain risks, excluding them from discussion because they were uncomfortable, politically awkward or considered not worth the cost of managing. A review rule that requires the team to discuss every risk above a set score, whether or not anyone wants to, protects the project from that kind of quiet avoidance.

Risk Categories

Risks are grouped in a simple risk breakdown structure: external (permits, weather, markets, utilities), site (soil, environmental conditions), contractor and procurement, design, organizational (city staffing, approvals), and operational readiness (systems, staffing for opening).

Probability and Impact Definitions

RatingProbabilityCost impactSchedule impact
1, very lowunder 10 percentunder $10,000under 1 week
2, low10 to 29 percent$10,000 to $49,9991 to 2 weeks
3, medium30 to 49 percent$50,000 to $149,9992 to 4 weeks
4, high50 to 69 percent$150,000 to $299,9991 to 2 months
5, very high70 percent or more$300,000 or moreover 2 months

The risk score is probability times the higher of the cost or schedule impact rating. Scores of 12 or more are high and require a response plan and steering committee review; 6 to 11 are medium and require an owner and response; 5 or less are low and are watched.

Tracking and Reporting

The register is kept on the project site. The project manager reports the top five risks and any new high risks in the biweekly status report, and closes risks when their trigger dates pass or the work they affect is complete. Each entry records its status as open, triggered or closed, the date of its last review and the result of any response carried out, so that the register shows not only what was feared but what was done.

Why this part earns its pointsThe register writes every risk as cause, risk and effect, and pairs each response with an owner and a trigger.
3

Part 2: Risk Register

IDRisk (cause, risk, effect)PIScoreResponseOwnerTrigger
R1Because borings were limited, unsuitable soil may be found under the gym slab, adding excavation cost and delay3412Mitigate: two added borings before mobilization; unit prices for over-excavation in the contractConstruction managerBoring results
R2Because steel is bought late, price increases may raise the structural cost339Mitigate: early purchase of steel through a contractor allowanceProcurement officerMill price index up 10 percent
R3Because the building permit review queue is long, permit issue may slip, delaying mobilization248Mitigate: pre-submittal meeting with the building departmentProject managerNo comments within 30 days
R4Because winter work is scheduled, cold weather may stop concrete and masonry work339Accept actively: schedule float and a cold-weather allowanceConstruction managerForecast lows below 25 degrees
R5Because only three bidders are expected, bids may exceed the estimate2510Mitigate: bid alternates for the kitchen and outdoor courtProcurement officerFewer than three bid intentions
R6Because the IT specialist works 15 percent, systems setup may lag, delaying opening339Transfer: use the network vendor contract for cabling and access controlIT specialistCabling not started by Month 9
R7Because user groups were consulted late, program needs may change during fit-out, causing rework236Avoid: freeze room layouts after the Month 4 user reviewProgram coordinatorChange requests after freeze
R8Because utility connections cross a public road, the utility company may delay its work236Mitigate: apply for service in Month 2 and confirm dates monthlyConstruction managerNo scheduled date by Month 6
R9Because the contractor's superintendent is assigned to two jobs, site supervision may be thin236Mitigate: contract requires a full-time superintendentConstruction managerSuperintendent absent two days a week
R10Because front desk staff are hired late, opening operations may be unready224Accept: watch; hiring requisition in Month 11Program coordinatorRequisition not approved
O1Because a state grant for energy efficiency is open, the project may obtain rebates that reduce cost339Exploit: grant application in Month 2Finance analystGrant notice of award

Expected Monetary Value and Contingency

RiskProbabilityCost if it occursExpected value
R1 unsuitable soil40 percent$280,000$112,000
R2 steel prices35 percent$140,000$49,000
R4 cold weather45 percent$90,000$40,500
R5 high bids25 percent$400,000$100,000
R6 systems delay40 percent$60,000$24,000
Other medium risksnot applicablenot applicable$94,500
Totalnot applicablenot applicable$420,000

The opportunity O1, if realized, would add about $60,000 to the reserve; it is not counted until awarded.

Managing the Reserve

The contingency reserve is not a general cushion. Each draw must name the risk in the register that occurred, the response that consumed the money and the amount, and the finance analyst records it in the contingency log. Draws of $25,000 or less need only the project manager's signature; anything larger goes to the steering committee, matching the thresholds in the communication plan. When a risk is closed without occurring, such as the cold-weather risk once the structure is enclosed, its expected value is released from the reserve and reported to the sponsor, who decides whether to return it to the budget or hold it for later risks. Tracking draws this way shows at each phase gate whether the original analysis was realistic.

Response Plans for the Highest Risks

Two risks need more than a line in the register. Risk R1, unsuitable soil under the gymnasium, scores 12 and is the largest single cost exposure. The response has two parts. Before the contractor mobilizes, the construction manager will order two added soil borings at the gym footprint, at a cost of about $8,000, which narrows the uncertainty while design changes are still cheap. The bid documents will also ask for unit prices for over-excavation and replacement fill, so if poor soil is found, the extra work is paid at a price set in competition rather than negotiated after the fact. If the borings show poor soil across the footprint, the structural engineer will evaluate a deeper slab design, and the project manager will bring the cost to the steering committee before bids open.

Risk R5, bids above the estimate, is scored 10 because its cost impact would be severe even though it is less likely. The response is to structure the bid with two deductive alternates, the teaching kitchen fit-out and the outdoor court, so the city can award a contract within budget without rebidding, which would cost about two months. The procurement officer will also contact regional contractors before advertising to confirm interest, since fewer than three bidders is the trigger that this risk is becoming real.

Secondary risks are recorded as well. Removing the kitchen alternate would affect the program coordinator's opening plans, so the communication plan's user group meetings will review that possibility in advance, and residual risk after each response is noted in the register.

Why this part earns its pointsThe biblical section ties prudence to the review rule, so the Scripture changes a practice rather than decorating the plan.
4

Biblical Integration

A proverb contrasts two travelers: the shrewd one spots danger ahead and shelters from it, while the careless one presses on and is hurt (English Standard Version Bible, 2001/2016, Proverbs 22:3). Spotting danger is the register's job, and sheltering from it, in practical terms, is the response plan. The verse also cuts against the deliberate ignorance Kutsch and Hall describe: a prudent team does not look away from a risk because it is unpleasant to discuss. That is why the plan requires every risk scored 12 or higher to be discussed with the steering committee, including risks that reflect on the city's own staffing.

Conclusion

The plan sets clear rules for identifying, scoring, responding to and reviewing risk on the recreation center, and the register applies them to the eleven risks known at contract award. The contingency reserve is tied to the analysis rather than to a rule of thumb, and the review schedule is designed to keep uncomfortable risks in view. Both documents will be updated at each phase gate.

5

References

Dinsmore, P. C., & Cabanis-Brewin, J. (Eds.). (2014). The AMA handbook of project management (4th ed.). AMACOM.

English Standard Version Bible. (2016). Crossway. (Original work published 2001)

Kutsch, E., & Hall, M. (2010). Deliberate ignorance in project risk management. International Journal of Project Management, 28(3), 245-255. https://doi.org/10.1016/j.ijproman.2009.05.003

Project Management Institute. (2013). A guide to the project management body of knowledge (PMBOK guide) (5th ed.). Project Management Institute.

What the BUSI 415 Week 6 instructions ask

In Week 6 students read chapter 11 of the PMBOK Guide, on risk management, watch a presentation and submit the Forum 3 replies, worth 50 points, alongside the third and largest of the scenario documents. The third project assignment produces both a risk register and a risk management plan for the instructor's scenario, following current PMBOK guidelines, grounded in the assigned textbook, at least one peer-reviewed study and a scriptural principle, cited in APA style. In the PMBOK Guide's fifth edition, the risk management plan comes from Plan Risk Management, while the register grows through Identify Risks, the two analysis processes and Plan Risk Responses, so a complete submission shows all of them working together.

How this BUSI 415 Week 6 example is built

The plan comes first because it sets the rules the register follows. It states the methodology, the roles of the project manager, risk owners and steering committee, the contingency budget and when risks are reviewed, and it defines probability and impact scales with a matrix that turns them into high, medium and low scores. The register then applies those rules to eleven risks, each with a cause and effect statement, a score, a response, an owner and a trigger. An expected monetary value table shows how the contingency reserve was sized. Kutsch and Hall's research on deliberate ignorance justifies requiring the team to review uncomfortable risks. The biblical integration and a short conclusion close the document.

BUSI 415 Week 6 grading rubric: where the points go

The risk project is graded on whether the plan and register follow the PMBOK Guide's risk processes and apply them to the scenario, whether the risks are specific and well analyzed, whether responses fit each risk, and whether the reading, outside research and Scripture are actually used and correctly cited. Instructors look for risks written as cause, risk and effect rather than vague worries, for probability and impact scales that are defined before they are used, and for a named owner and trigger for each response. Including opportunities as well as threats, and linking contingency reserves to the analysis, shows complete command of the chapter.

BUSI 415 Week 6 help: mistakes that cost points

Write the plan's scales and matrix before scoring a single risk, so scores mean something. Draw risks from every part of your scenario, including the resource and communication plans you already wrote. State each risk in a cause, risk and effect sentence. Name each response by its PMBOK strategy, and give each an owner and a trigger. Add at least one opportunity. If you calculate expected monetary value, label the probabilities and costs as estimates. Use your scholarly article to justify a rule in the plan, such as how often risks are reviewed. Keep the register as a table, and check that its roles match your earlier plans.

Related BUSI 415 sample papers

Other BUSI 415 weeks

More BS in Business Administration sample papers

BUSI 415 Week 6 questions, answered

What is the BUSI 415 Risk Register and Risk Management Plan?

Week 6's 150-point project in BUSI 415: rules for managing risk plus a scored list of the scenario's risks, both following the PMBOK Guide and supported by the textbook, research and Scripture.

Where can I find a free BUSI 415 Week 6 sample paper?

Read the whole BUSI 415 Week 6 risk management plan on this page, and register for a composite recreation center, with scales, a matrix, eleven analyzed risks and an expected monetary value table.

What is the difference between a risk register and a risk management plan?

The plan sets the rules for risk work, such as methods, roles, budget, timing, categories and scoring scales; the register lists the specific risks with their analysis, responses, owners and status.

How do you calculate expected monetary value for a risk?

Multiply the probability of the risk by its impact in dollars; summing the values for the risks being covered by a reserve gives one basis for sizing a contingency reserve.

What else is due in BUSI 415 Module/Week 6?

Two responses to classmates' risk threads, 250 to 350 words apiece and 50 points together, are due as well, with the PMBOK Guide's eleventh chapter and a presentation as reading.

Use it as a model, or ask for your own

This paper is an original model written by our desk for study. It is not a submitted student paper and not an official Liberty University document. Read it for structure and reasoning, then write your own to the instructions in your Canvas course. If you want a version built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.