BUSI 415 Week 8 Project: Procurement Management Plan Example

Reviewed by Thomas Kerrigan, MBA, CPA · Liberty University · Updated

This BUSI 415 Week 8 sample is the last of the four project assignments, a procurement management plan completing the composite recreation center scenario. It works through make-or-buy decisions, divides the purchases into five procurement packages, assigns a contract type to each with reasons drawn from research on procurement incentives, and sets out the procurement documents, source selection criteria with weights, a procurement schedule, roles, contract administration and change control, and how contracts will be closed. Links to the earlier risk register show which risks the contracts transfer and which the city keeps. Deuteronomy on paying hired workers promptly supplies the biblical integration, applied to the city's payment terms for small subcontractors. Liberty University BUSI 415 grades the procurement plan at 150 points in the final week, completing the recreation center scenario that BS in Business Administration students opened with the Week 2 resource plan.

CourseBUSI 415 Advanced Project Management (BUSI415)
Module/Week8
AssignmentProject: Procurement Management Plan
Paper typeProject procurement management plan
Lengthabout 1,007 words, 4 double-spaced pages plus title page and references. Course guide: a project plan following current PMBOK guidelines, with 1 biblical integration, the course textbook and at least 1 scholarly article, in current APA format
FormatAPA 7 student paper
Points150
SchoolLiberty University Online
ProgramBS in Business Administration
Where it sitsModule/Week 8 in Liberty's published BUSI 415 course guide; current sections can differ
UpdatedOctober 2026

Free sample paper for BUSI 415 Week 8

1

Procurement Management Plan: Fairmont Hills Community Recreation Center

 

[Student Name]

School of Business, Liberty University

BUSI 415: Advanced Project Management

Project: Procurement Management Plan

[Instructor Name]

[Date]

 

The city, the project, its policies and its purchases are composites standing in for the instructor's scenario; the PMBOK Guide, the handbook and the research cited are real.

Why this part earns its pointsThe introduction ties procurement to the PMBOK process and to the city's purchasing rules, which constrain every later choice.
2

Procurement Management Plan: Fairmont Hills Community Recreation Center

Purpose and Constraints

This plan describes how the City of Fairmont Hills will acquire the goods and services needed for the community recreation center. It applies Plan Procurement Management as the PMBOK Guide describes it (Project Management Institute, 2013) within the limits of the city's purchasing ordinance, which requires sealed competitive bids for construction contracts above $100,000, allows competitive proposals for professional services and technology, and requires council approval of any contract above $250,000. Dinsmore and Cabanis-Brewin (2014) note that public projects must plan procurement around such rules from the start, since they fix much of the schedule. The plan uses the roles from the resource plan and responds to the risks recorded in the project's risk register.

Several assumptions underlie it. The design documents are complete and approved, so construction can be bid on a fixed price. The city's general fund and a bond issue cover the budget, so no purchase depends on outside financing, except the energy rebate, which is treated as an opportunity. And the purchasing division can give the procurement officer the time listed in the resource calendar during bidding. Should one of these prove false, the affected package and its contract type will be reconsidered through change control, with the steering committee informed.

Make-or-Buy Decisions

NeedDecisionReason
Building constructionBuyThe city has no construction workforce
Construction inspectionMakePublic Works engineers inspect city buildings and know the code
Network cabling and access controlBuyThe IT specialist works 15 percent; this transfers risk R6
Furniture, fitness and kitchen equipmentBuyStandard products available from many vendors
Registration and membership softwareBuyThe city lacks software developers; a hosted product is cheaper to support
Opening eventMakeParks and Recreation staff run events regularly

Procurement Packages and Contract Types

Why this part earns its pointsEach contract type is justified by how well the work can be defined, applying the research rather than listing definitions.
3

The choice of contract type follows how well each package can be defined. In Bajari and Tadelis's (2001) model, a fixed price motivates the seller to hold down cost, yet each change then has to be bargained over, which makes fixed prices efficient for straightforward, fully specified work and cost reimbursement better for complex work that will evolve. Turner and Simister (2001) reach a parallel conclusion: the less certain the deliverable and the method of producing it, the more the contract should share risk rather than fix it.

PackageEstimated valueContract typeReason
P1 General construction$5,200,000Firm fixed price with unit prices for over-excavationDesign is complete; unit prices share the soil risk R1 instead of inviting inflated bids
P2 Structural steel allowance$380,000 within P1Fixed price with economic price adjustmentLets the contractor buy early while sharing steel price risk R2
P3 Cabling and access control$210,000Fixed price under the city's existing vendor contractScope is defined by the drawings; transfers schedule risk R6
P4 Furniture and equipment$420,000Firm fixed price, by lotStandard products, easily specified
P5 Registration software$45,000 per yearFixed annual subscription with implementation at time and material, capped at $30,000Configuration needs are uncertain until staff test the system

The one package with real uncertainty, software configuration, is the one that does not get a firm fixed price. Using a cap keeps the city's exposure known while avoiding the change disputes a fixed price would invite.

Procurement Documents and Source Selection

Package P1 will use an invitation for bid with complete drawings and specifications, and award goes to the lowest responsive and responsible bidder, as the ordinance requires; bid alternates for the kitchen and outdoor court respond to risk R5. Packages P4 and P5 will use requests for proposals evaluated on the criteria below.

CriterionP4 weightP5 weight
Price4030
Meets specifications and functional requirements2530
Experience with public facilities1015
Delivery or implementation schedule1510
References and support1015
Total100100

An evaluation panel of three, the procurement officer, the program coordinator and the IT specialist for P5 or the construction manager for P4, will score proposals independently before meeting. Scores are averaged, and the panel discusses any criterion on which members differ by more than two points before finalizing them. The two highest-scoring software vendors will be asked to demonstrate their systems using scripted scenarios, such as registering a family for a summer camp and issuing a refund, so that the functional score reflects what staff will actually do. Price proposals are opened only after the technical scores are recorded, which keeps the panel from being anchored by cost.

Procurement Schedule

PackageSolicitation issuedAwardCouncil approvalDelivery or completion
P1 constructionMonth 1, week 1Month 2, week 2Month 2, week 3Month 13
P3 cablingMonth 7Month 8Not requiredMonth 11
P4 furnitureMonth 9Month 10Month 10Month 13
P5 softwareMonth 8Month 9Not requiredMonth 12, staff trained Month 13

Local and Small Business Participation

The city's purchasing ordinance encourages participation by local and small businesses without setting quotas. The procurement officer will advertise the construction bid through the regional builders' exchange and hold a pre-bid meeting at which the general contractors can meet local subcontractors. For the furniture package, the lot structure allows smaller dealers to bid on individual lots, such as fitness equipment or kitchen equipment, rather than the whole package. These steps widen competition, which also supports the response to risk R5, too few bidders.

Roles and Authority

The procurement officer issues solicitations, receives bids and proposals, and drafts contracts. The project manager approves technical requirements and recommends award. The city manager signs contracts up to $250,000; the council approves larger ones. Only the procurement officer may communicate with bidders during a solicitation, to keep the process fair.

Why this part earns its pointsAdministration and change control show the plan working after award, which is where most procurement disputes arise.
4

Contract Administration and Change Control

The construction manager administers P1, reviewing monthly pay applications against work in place and retaining 5 percent until final completion. Contract changes are handled through the integrated change control process: the contractor submits a change request with cost and time, the construction manager reviews it, and approval follows the thresholds in the communication plan. Claims are logged and answered in writing within fourteen days. Seller performance is reviewed at each monthly progress meeting. For the construction contract, the construction manager tracks schedule progress against the contractor's baseline, the number of open requests for information and their age, inspection failures and safety incidents. For the furniture and software vendors, the procurement officer tracks delivery dates and defects. A seller that falls behind receives a written notice describing the problem and asking for a recovery plan within seven days, and repeated problems are documented for the city's vendor performance file, which is consulted in future awards. Most disputes are expected to be settled at the project level; those that are not go to the city attorney.

Closing Procurements

Each contract is closed after the work is accepted, warranties and manuals are received, final payment is made and lessons learned are recorded. Retainage on P1 is released after the punch list is complete and the certificate of occupancy is issued. Procurement files are kept for the period required by the city's records schedule.

Biblical Integration

Deuteronomy forbids taking advantage of a poor laborer and tells employers to hand over the day's pay before nightfall, since the worker is counting on it (English Standard Version Bible, 2001/2016, Deuteronomy 24:14-15). Small subcontractors on a public project often wait months for money that has already been paid to the general contractor. This plan therefore requires P1 to include a prompt payment clause that gives the contractor ten days after each city payment to pass the money on to its subcontractors, and the construction manager will check payment certifications with each pay application.

Conclusion

This plan sets out what the city will make and buy, how each package will be contracted and why, how sellers will be selected and managed, and how contracts will be closed. Its contract choices respond directly to the risks identified in the risk register, completing a set of plans in which staffing, communication, risk and procurement fit one another.

5

References

Bajari, P., & Tadelis, S. (2001). Incentives versus transaction costs: A theory of procurement contracts. RAND Journal of Economics, 32(3), 387-407. https://doi.org/10.2307/2696361

Dinsmore, P. C., & Cabanis-Brewin, J. (Eds.). (2014). The AMA handbook of project management (4th ed.). AMACOM.

English Standard Version Bible. (2016). Crossway. (Original work published 2001)

Project Management Institute. (2013). A guide to the project management body of knowledge (PMBOK guide) (5th ed.). Project Management Institute.

Turner, J. R., & Simister, S. J. (2001). Project contract management and a theory of organization. International Journal of Project Management, 19(8), 457-464. https://doi.org/10.1016/S0263-7863(01)00051-5

What the BUSI 415 Week 8 instructions ask

The final week assigns chapter 12 of the PMBOK Guide, on procurement management, and a presentation, and it closes the course with the Forum 4 replies, two of 250 to 350 words worth 50 points, and this fourth project assignment, worth 150 points; everything is due by Friday night. The procurement management plan answers the instructor's scenario following current PMBOK guidelines, uses the textbook, one or more journal articles and Scripture, with all sources in APA style. In PMBOK's fifth edition, the plan comes from Plan Procurement Management and covers contract types, procurement documents, source selection, coordination with the schedule, constraints and how sellers will be managed.

How this BUSI 415 Week 8 example is built

The plan follows the order a procurement officer would work in. It starts with make-or-buy analysis, then groups the purchases into packages and gives each a contract type, explaining the choice with Bajari and Tadelis's trade-off between cost incentives and the cost of changes and with Turner and Simister's link between uncertainty and contract form. A table of evaluation criteria and weights shows how the furniture and systems vendors will be chosen, and a schedule ties every award to the project calendar. Sections on roles, contract administration, change control and closure follow, with cross-references to risks R1, R2, R5 and R6 from the register. The biblical integration shapes a prompt payment rule.

BUSI 415 Week 8 grading rubric: where the points go

The procurement plan is graded on how fully it applies the PMBOK Guide's procurement planning to the scenario, on the soundness of its make-or-buy decisions and contract type choices, on clear source selection criteria, and on whether the reading, research and Scripture are applied rather than merely cited. Instructors want each contract type explained by the work it covers and the risk it moves, and a plan that connects to the schedule and to the risks identified in Week 6. Defined roles for the procurement officer and project manager, and a process for changes and claims, show the plan could actually be used.

BUSI 415 Week 8 help: mistakes that cost points

List every purchase your scenario needs, then decide what to make in-house and what to buy, giving a reason for each. Group purchases into packages that suit how sellers work, and choose a contract type for each based on how well the work can be defined. Write source selection criteria with weights that add to 100. Put the procurement schedule in a table tied to your project calendar. Name who signs contracts and who approves changes. Point back to specific risks in your Week 6 register that the contracts transfer or share with sellers, naming each by its ID. Use research to justify contract types. Finish early, since the Forum 4 replies share the week and the course shuts on Friday.

Related BUSI 415 sample papers

Other BUSI 415 weeks

More BS in Business Administration sample papers

BUSI 415 Week 8 questions, answered

What is the BUSI 415 Procurement Management Plan?

The closing BUSI 415 project, 150 points in the final week: a plan for purchasing what the scenario needs, following the PMBOK Guide and resting on the textbook, research and Scripture.

Where can I find a free BUSI 415 Week 8 sample paper?

Scroll down for the whole BUSI 415 Week 8 procurement management plan, with make-or-buy decisions, five contract packages, weighted selection criteria, a procurement schedule and contract administration.

What goes in a procurement management plan?

Make-or-buy decisions, contract types, procurement documents, source selection criteria, the procurement schedule, roles and authority, constraints such as purchasing law, contract administration, change control and how contracts will be closed.

What are source selection criteria?

The factors a buyer uses to evaluate proposals, such as price, technical approach, experience, references and schedule, usually given weights so that proposals can be scored and compared consistently.

What else is due in BUSI 415 Module/Week 8?

The last replies, two answers to Forum 4 threads of 250 to 350 words for 50 points, after the PMBOK Guide's procurement chapter and a presentation; the course closes Friday at 11:59 p.m.

Use it as a model, or ask for your own

This paper is an original model written by our desk for study. It is not a submitted student paper and not an official Liberty University document. Read it for structure and reasoning, then write your own to the instructions in your Canvas course. If you want a version built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.