| Course | MGMT 610 Risk Management (MGMT610) |
|---|---|
| Module/Week | 6 |
| Assignment | Risk Management Plan |
| Paper type | Risk management plan |
| Length | about 1,768 words, 6 double-spaced pages plus title page and references. Course guide: per the course guide, an 8-10-page plan with a title page, an introduction, project description, risk scope and objectives, risk management methodology, tools and risk communication plan, a reference page with at least three references, and appendices holding a Risk Assessment Form, a Risk Assessment Matrix and a Risk Response Matrix |
| Format | APA 7 student paper |
| Points | 200 |
| School | Liberty University Online |
| Program | MS in Management and Leadership |
| Where it sits | Module/Week 6 in Liberty's published MGMT 610 course guide; current sections can differ |
| Updated | October 2026 |
Free sample paper for MGMT 610 Week 6
Risk Management Plan: Construction of a 72-Bed Behavioral Health Hospital
[Student Name]
School of Business, Liberty University
MGMT 610: Risk Management
Risk Management Plan
[Instructor Name]
[Date]
The contractor, the hospital project and every figure in the plan are composites standing in for the project a student plans; the PMBOK Guide, Wilson's text and the studies cited are real; the requirements follow Liberty's public course guide for MGMT 610.
Risk Management Plan: Construction of a 72-Bed Behavioral Health Hospital
Introduction
This plan describes how the project team will identify, analyze, respond to and monitor risks during the construction of a 72-bed behavioral health hospital. It is written for the contractor's project leadership, the two owners in the hospital's joint venture and the design team, and it will be reviewed at each phase gate. It follows the PMBOK Guide's sequence for project risk (Project Management Institute, 2017) and the planning approach of Wilson (2015), adapted to a construction project that must end with state licensure and accreditation before the hospital can admit a patient.
Project Description
The hospital is a three-story, 96,000-square-foot building on a regional health system's main campus, connected to the existing medical center by an enclosed corridor. It will hold 72 inpatient beds in six units, including an adolescent unit, along with an intake area, outdoor courtyards and support space. Ownership sits with a joint venture in which the health system partners with a behavioral health company that operates hospitals in several states. The contractor is serving as construction manager at risk under a guaranteed maximum price of $68 million, which includes a construction contingency of $2.4 million. Construction is scheduled for 22 months, from site mobilization in March to substantial completion the following December, with licensing surveys planned for January and the first admissions in February. The design team is completing construction documents now, and early packages for the foundation and steel have been released.
The project has several stakeholders whose interests shape its risks. The health system needs the building to connect safely to an operating hospital without disrupting patient care. The behavioral health operator, which will run the hospital, sets the clinical program and the environment-of-care standards, and its clinical leaders will review mockups of patient rooms. Licensure comes from the state health department, and an accrediting body surveys it before payers will contract with it. Neighbors along the campus's south edge have asked for limits on truck traffic and night work, which the city included as conditions of the site plan approval.
Risk Scope and Objectives
The plan covers risks from the release of the early design packages through the end of the licensing and accreditation surveys. It includes risks to schedule, cost, quality and safety arising from design, procurement, labor, site conditions, regulation and the owners' decisions. It excludes the operator's own risks in hiring clinical staff and in obtaining payer contracts, which the operator manages separately, except where those risks change the construction schedule.
The plan supports four objectives. First, substantial completion by December 15, so that licensing surveys can begin in January. Second, completion within the guaranteed maximum price, with contingency use reported monthly. Third, a building that passes its state licensing and accreditation surveys on the first visit, with no deficiency that delays admissions. Fourth, zero lost-time injuries among workers on the site. Risks are judged by their potential effect on these four objectives.
The plan rests on several assumptions and constraints. It assumes that construction documents will be complete by May, that the owners will respond to requests for information within ten working days, and that the state will schedule its licensing survey within three weeks of the request. It is constrained by the guaranteed maximum price, by the city's limits on work hours along the south edge, and by the infection control requirements that apply wherever the new building meets the existing hospital. If any assumption fails, the risk manager will add a corresponding risk to the register.
Risk Management Methodology
The team will follow the PMBOK Guide's sequence of risk processes: identify risks, perform qualitative analysis, perform quantitative analysis for the largest risks, plan responses, implement responses and monitor risks (Project Management Institute, 2017). Each step has an owner and a schedule.
Roles. The contractor's project executive is accountable for the plan. A senior project manager serves as risk manager, maintains the register and runs the reviews. Every risk in the register has one owner, named by role, who is responsible for its response and for reporting changes. The owners' representative and the architect each name a risk lead who attends the monthly review.
Risk categories. Risks are organized in a breakdown structure with six categories: design, procurement and supply, labor, site conditions, regulatory and owner. The categories follow the industry analysis from the company's case study and help the team check that no area has been overlooked during identification.
Identification. Initial identification draws on the industry risk categories from the company's case study profile, a review of drawings and specifications, lessons-learned files from three prior healthcare projects and a structured workshop with the design team and major subcontractors. Any team member may submit a new risk at any time using the Risk Assessment Form in Appendix A.
Qualitative analysis. Each risk is scored for probability and for impact on each of the four objectives on five-point scales. Probability ranges from 1, under 10 percent, to 5, over 70 percent. For schedule, an impact of 1 is a delay of under one week and 5 is a delay of more than eight weeks. For cost, 1 is under $50,000 and 5 is more than $1 million. For licensure, 5 is a deficiency that would delay admissions. The highest impact score across objectives is multiplied by probability, and the result places the risk in the matrix in Appendix B. A product of 15 to 25 marks a high risk, one from 8 through 14 a moderate risk, and anything under 8 a low one.
Quantitative analysis. Because a matrix can give two very different risks one score, and can even place the cheaper risk higher (Cox, 2008), the team will not rely on matrix scores to size contingency. Instead, all high risks and any moderate risk with a cost impact over $250,000 receive three-point estimates of cost and duration. A Monte Carlo model of the budget and the schedule, of the kind Kwak and Ingall (2007) describe, will be run at each phase gate to estimate the probability of meeting the guaranteed maximum price and the December completion date, and to test whether the contingency is sufficient.
Response planning. Each high and moderate risk receives a response chosen from the PMBOK Guide's strategies for threats: avoid, transfer, mitigate or accept, with escalation for risks outside the project's authority (Project Management Institute, 2017). Responses, owners and triggers are recorded in the Risk Response Matrix in Appendix C.
Contingency management. The $2.4 million construction contingency is held by the contractor and released by the project executive on the risk manager's recommendation. Each draw is recorded against the risk that caused it, so the team can compare actual contingency use with the Monte Carlo forecast. If the model shows less than a 70 percent chance that remaining contingency will cover remaining risk, the project executive will review the response plans with the owners before any further scope is added.
Monitoring. The risk manager reviews the register weekly with the superintendent and holds a full risk review monthly with all risk leads. Risks are re-scored at each review, closed when their window has passed, and new risks are added as work proceeds.
Tools
Four tools support the methodology. The Risk Assessment Form (Appendix A) records each risk when it is first raised: a three-part statement of what could cause the risk, what might happen and what it would do to the project, its category, its probability and impact scores, the objectives it threatens, its proposed owner and any early warning signs. The Risk Assessment Matrix (Appendix B) displays probability against impact and divides the scores into high, moderate and low bands, giving the team a common picture of where each risk sits. The Risk Response Matrix (Appendix C) lists the ten highest risks with their strategy, specific actions, owner, trigger and residual score after response. All three feed a risk register kept in the contractor's project management software, where each entry carries its history of scores, so the team can see whether a risk is growing or shrinking. Wilson (2015) emphasizes that planning tools are only useful when they are kept current, and the register is the record the monthly review works from. The Monte Carlo model is the fourth tool. It is built in a spreadsheet add-in using the three-point estimates recorded on the assessment forms, and it produces two charts for each phase gate: the probability distribution of final cost against the guaranteed maximum price, and the distribution of the substantial completion date against December 15. The model will treat related risks, such as concrete and steel price escalation, as correlated rather than independent, so the results do not appear more certain than they are.
Risk Communication Plan
Risk information will reach each audience at a frequency suited to its role. The superintendent and foremen review field-level risks at the weekly coordination meeting. The project team, owners' representative and design team receive the full register and a summary of changes before each monthly risk review. The joint venture's steering committee receives a one-page risk dashboard each month, showing the top ten risks, contingency use and the most recent Monte Carlo results. Subcontractors receive the risks that affect their scope at their monthly meetings. The dashboard uses plain language rather than risk scores alone: each top risk is described in one sentence, with its owner, its trend since the last report and the next action due. Contingency is shown as a bar comparing the amount used with the amount the model predicted would be used by that date. This format lets owners who do not read the full register see quickly whether the project's risk position is improving.
Escalation does not wait for the calendar. Any risk whose score rises to 15 or more between reviews, or any event that consumes more than $100,000 of contingency, is reported by its owner to the risk manager within one business day, and by the risk manager to the project executive and the owners' representative within two. Any risk that threatens the December completion date by more than four weeks is reported to the steering committee within one week. Closed risks and lessons learned are summarized at each phase gate and in the project's closeout report.
Conclusion
This plan gives the team a shared method for treating uncertainty on a project that cannot slip without delaying care for patients waiting for psychiatric beds. Its scales and thresholds make risk scores comparable, and its quantitative analysis keeps contingency tied to dollars rather than colors. Its communication plan ensures that a risk that grows between meetings reaches the people who can act. The plan will be revised at each phase gate as design is completed and construction proceeds.
Appendix A: Risk Assessment Form
| Field | Entry |
|---|---|
| Risk ID and date raised | R-014, March 12 |
| Raised by | Electrical subcontractor's project manager |
| Risk statement (cause, event, effect) | Because the regional market is short of journeyman electricians, the subcontractor may be unable to staff the low-voltage installation at peak, delaying systems commissioning and the licensing surveys |
| Category | Labor |
| Objectives affected | Schedule, licensure |
| Probability (1-5) | 3 |
| Impact (1-5) | 4 (schedule delay of four to eight weeks) |
| Score | 12 (moderate) |
| Early warning signs | Crew size below plan for two consecutive weeks; overtime above 15 percent |
| Proposed owner | Senior project manager, MEP |
| Proposed response | Mitigate: commit second low-voltage subcontractor; preassemble devices off site |
Appendix B: Risk Assessment Matrix
| Probability / Impact | 1 Minimal | 2 Minor | 3 Moderate | 4 Major | 5 Severe |
|---|---|---|---|---|---|
| 5 Over 70% | 5 Low | 10 Moderate | 15 High | 20 High | 25 High |
| 4 50-70% | 4 Low | 8 Moderate | 12 Moderate | 16 High | 20 High |
| 3 30-49% | 3 Low | 6 Low | 9 Moderate | 12 Moderate | 15 High |
| 2 10-29% | 2 Low | 4 Low | 6 Low | 8 Moderate | 10 Moderate |
| 1 Under 10% | 1 Low | 2 Low | 3 Low | 4 Low | 5 Low |
Appendix C: Risk Response Matrix
| ID | Risk | Score | Strategy | Actions | Owner | Trigger | Residual |
|---|---|---|---|---|---|---|---|
| R-003 | Ligature-resistant doors and hardware delivered late | 20 | Mitigate | Release order with early package; approved second supplier; monthly factory check | Procurement manager | Shop drawings not approved by June 1 | 8 |
| R-007 | Licensing survey finds environment-of-care deficiencies | 16 | Mitigate | Mock survey with former surveyor in November; owner sign-off on room mockups | Project executive | Mockup punch list over 20 items | 6 |
| R-014 | Electrician shortage at peak | 12 | Mitigate | Second low-voltage subcontractor; off-site preassembly | Senior PM, MEP | Crew below plan two weeks | 6 |
| R-002 | Concrete and steel price escalation | 15 | Transfer | Escalation clause for rebar; early buyout of steel | Chief estimator | Supplier quote validity under 30 days | 6 |
| R-009 | Owner design changes after pricing | 15 | Mitigate | Change freeze date; joint venture decision log with 10-day response | Owners' representative | Request after freeze | 9 |
| R-011 | Unforeseen soil conditions | 10 | Accept | Allowance in contingency; borings at corridor link | Superintendent | Excavation finds unsuitable soil | 10 |
| R-005 | Infection control limits near corridor link | 12 | Mitigate | Approved ICRA plan; negative-pressure barriers; night work for tie-in | Superintendent | Hospital requests work stop | 6 |
| R-016 | Plumbing fixture installation errors | 9 | Mitigate | First-room mockup; installer training by manufacturer | Senior PM, MEP | Failed mockup inspection | 4 |
| R-020 | Worker injury during steel erection | 10 | Mitigate | Site-specific safety plan; daily pre-task meetings | Safety manager | Near-miss report | 5 |
| R-022 | Joint venture dispute delays approvals | 8 | Escalate | Steering committee resolution path in contract | Project executive | Approval past 10 days | 8 |
References
Cox, L. A., Jr. (2008). What's wrong with risk matrices? Risk Analysis, 28(2), 497-512. https://doi.org/10.1111/j.1539-6924.2008.01030.x
Kwak, Y. H., & Ingall, L. (2007). Exploring Monte Carlo simulation applications for project management. Risk Management, 9(1), 44-57. https://doi.org/10.1057/palgrave.rm.8250017
Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK guide) (6th ed.).
Wilson, R. (2015). Mastering risk and procurement in project management: A guide to planning, controlling, and resolving unexpected problems. Pearson FT Press.
What the MGMT 610 Week 6 instructions ask
The Risk Management Plan falls in Module/Week 6 of MGMT 610 with chapter 5 of Wilson and a presentation, and no other MGMT 610 assignment is worth as much. The guide asks for eight to ten pages and spells out the contents. The body must contain an introduction, a description of the project, the risk scope and objectives, the risk management methodology, the tools to be used and the risk communication plan. Three tools must be built and placed in appendices: a Risk Assessment Form, a Risk Assessment Matrix and a Risk Response Matrix. The format also calls for a title page, plus a reference page listing three sources or more. Many students build the plan on the organization they profiled in the Week 3 Case Study, which lets the industry risks they identified there feed directly into the response matrix.
How this MGMT 610 Week 6 example is built
After stating whom the plan serves, the sample describes the project: a three-story behavioral health hospital on a health system's campus, built over 22 months under a $68 million guaranteed maximum price. The scope section states which risks the plan covers, from design through licensing, and sets four objectives for opening date, cost, licensure and safety. The methodology follows the PMBOK Guide's risk processes and defines five-point probability and impact scales, risk thresholds, owners and a monthly review cycle, with a Monte Carlo cost model used only for the largest risks, given what Cox shows about the limits of matrices. The tools section explains the form, matrix and register, and the communication plan sets audiences, frequencies and escalation rules. Three appendices hold the charts.
MGMT 610 Week 6 grading rubric: where the points go
The plan is graded on whether every required element is present and whether the elements form a usable plan. Readers check for the introduction, project description, risk scope and objectives, methodology, tools and communication plan in the body, and for the three charts in appendices, and for the title page and the minimum of three references. Beyond the checklist, strong plans define their scales and thresholds so that two people would score a risk the same way, assign each risk an owner, and connect the response strategies to the risks identified. The communication plan should say who hears what, when and how. Clear writing, consistent terminology from the PMBOK Guide and Wilson, and current APA format finish the evaluation within the eight-to-ten-page range.
MGMT 610 Week 6 help: mistakes that cost points
The weakest plans describe risk management in general instead of planning it for one project. Name the project, its dates and its budget, and make every section specific to them. Define probability and impact scales with numbers, such as a delay of more than four weeks counting as a five, so the matrix means something. Do not let the appendices drift from the body: the response matrix should list the same top risks the methodology prioritized. Use the PMBOK Guide's response strategies, avoid, transfer, mitigate and accept for threats, consistently. Give each risk a single owner by role. Keep the communication plan practical, with an escalation rule for risks that cross a threshold between meetings, and check the page count with the appendices excluded.
Related MGMT 610 sample papers
Other MGMT 610 weeks
- MGMT 610 Week 1: Reflection Post: A Realized Risk
- MGMT 610 Week 2: Forum 1: Risks Nobody Named
- MGMT 610 Week 3: Case Study: Contractor Risk Profile
- MGMT 610 Week 4: Forum 2: Risk Matrices and Numbers
- MGMT 610 Week 5: Forum 3: Contracts and Risk Transfer
- MGMT 610 Week 7: Forum 4: Early Warning Signs
More MS in Management and Leadership sample papers
- MGMT 501 Week 6: Group Forum 5: Resilient Teams
- MGMT 602 Week 6: Forum 3 Replies: Merge or Stay Apart
MGMT 610 Week 6 questions, answered
What is the MGMT 610 Risk Management Plan?
The 200-point assignment due in Module/Week 6: an eight-to-ten-page plan covering the project, risk scope and objectives, methodology, tools and communication, with three charts in appendices.
Where can I find a free MGMT 610 Week 6 sample paper?
A complete MGMT 610 Week 6 risk management plan for a 72-bed behavioral health hospital, with its assessment form, matrix and response matrix, is reproduced on this page.
What charts does the MGMT 610 risk plan need?
Three, placed in appendices: a Risk Assessment Form for recording each risk, a Risk Assessment Matrix for scoring probability against impact, and a Risk Response Matrix for strategies and owners.
What are the four responses to a negative risk?
The PMBOK Guide's sixth edition lists avoid, transfer, mitigate and accept for threats, with escalation added for risks outside the project's authority.
How many references does the MGMT 610 risk plan require?
At least three, listed on a reference page; this sample cites the PMBOK Guide, Wilson's text and two peer-reviewed articles on risk matrices and simulation.
Use it as a model, or ask for your own
This paper is an original model written by our desk for study. It is not a submitted student paper and not an official Liberty University document. Read it for structure and reasoning, then write your own to the instructions in your Canvas course. If you want a version built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.