| Course | BUSI 681 Advanced Project Management II (BUSI681) |
|---|---|
| Module/Week | 8 |
| Assignment | Case Study: Project Model Part 2 |
| Paper type | Project model, part 2 of 2 (Microsoft Project plan) |
| Length | about 837 words, 3 double-spaced pages plus title page and references. Course guide: the second half of the project model, built in Microsoft Project, with a detailed project description, a list of principal deliverables and a breakdown of all necessary tasks with dates, costs and resources |
| Format | APA 7 student paper |
| Points | 150 |
| School | Liberty University Online |
| Program | MBA |
| Where it sits | Module/Week 8 in Liberty's published BUSI 681 course guide; current sections can differ |
| Updated | October 2026 |
Free sample paper for BUSI 681 Week 8
Maple Hill Lead Service Line Replacement, Phase 1: Microsoft Project Schedule with Deliverables, Task Breakdown, Dates, Costs and Resources
[Student Name]
School of Business, Liberty University
BUSI 681: Advanced Project Management II
Case Study: Project Model Part 2
[Instructor Name]
[Date]
The utility, the neighborhood, the dates and every cost and hour in the schedule are composites continuing Part 1 and were computed for this sample; the federal rule, the textbook and the research cited are real, and the required contents follow Liberty's public course guide for BUSI 681.
Maple Hill Lead Service Line Replacement, Phase 1: Microsoft Project Schedule with Deliverables, Task Breakdown, Dates, Costs and Resources
1. Project Description
Phase 1 of Riverbend Water's lead service line replacement program removes all 420 known lead service lines in the Maple Hill neighborhood, putting copper in place of the public and the private sections of each line alike, from the main to the meter. Full replacement is the point of the project: research on partial replacements found that cutting out only part of a lead line can raise lead release in household plumbing in the short term, and the federal Lead and Copper Rule Improvements generally require systems to remove lead service lines in full over the coming decade (U.S. Environmental Protection Agency [EPA], 2024).
The schedule runs from March 1, 2027, to a computed finish of November 29, 2027, using a calendar of five working days a week with six federal holidays removed. The work has four stages. Preparation covers the charter, the state loan, field verification of each line and the design and permits. Procurement selects a replacement contractor through competitive bidding. Customer outreach secures signed access agreements from property owners. Construction then replaces lines in three blocks of 140, followed by restoration, filter distribution, follow-up sampling, the inventory update and closeout. The budget is $5.30 million, and the plan's resource-loaded cost baseline is $4,935,680, leaving a contingency reserve of $364,320, about 7 percent of the budget, held outside the baseline under the sponsor's control. Excluded from the project are household plumbing beyond the meter, water main replacement and the other eight neighborhoods.
2. Principal Deliverables
- 1. Approved project charter and executed state loan agreement.
- 2. Field-verified material record for each of the 420 addresses.
- 3. Stamped replacement design and street-opening permits.
- 4. Executed unit-price construction contract.
- 5. Signed access agreements from property owners.
- 6. 420 full replacements, each with before and after photographs and a completion form.
- 7. Restored sidewalks, driveways and lawns, inspected within 14 days of each replacement.
- 8. Filters and six months of cartridges delivered to every household, and a sampling report covering 100 homes.
- 9. Updated service line inventory and a closeout report with cost per line and lessons for Phase 2.
3. Resource Sheet
| Resource | Type | Rate or unit cost | Units or hours | Total |
|---|---|---|---|---|
| Project manager | Work | $75 per hour | 640 hours | $48,000 |
| Engineering design | Work | $85 per hour | 352 hours | $29,920 |
| Customer outreach staff | Work | $48 per hour | 580 hours | $27,840 |
| Water quality lab staff | Work | $60 per hour | 60 hours | $3,600 |
| Finance analyst | Work | $60 per hour | 32 hours | $1,920 |
| Locate contractor | Cost | $450 per address | 420 | $189,000 |
| Replacement contractor | Cost | $9,800 per line | 420 | $4,116,000 |
| Restoration contractor | Cost | $1,100 per line | 420 | $462,000 |
| Filters and cartridges | Material | $95 per household | 420 | $39,900 |
| Printing, mailing and meeting costs | Cost | Lump sums | 2 | $13,000 |
| Laboratory analysis | Cost | $45 per sample | 100 | $4,500 |
| Total | $4,935,680 |
Construction and restoration together cost $10,900 per line, under the $11,500 ceiling set as a success criterion in Part 1.
4. Task Breakdown
| ID | Task | Days | Start | Finish | Predecessors | Resources |
|---|---|---|---|---|---|---|
| 1.1 | Charter approval and kickoff | 5 | Mar 1 | Mar 5 | none | Project manager, design, outreach, finance |
| 1.2 | Loan agreement executed | 20 | Mar 8 | Apr 2 | 1.1 | Finance, project manager |
| 2.1 | Field verification of 420 service lines | 30 | Mar 8 | Apr 16 | 1.1 | Locate contractor, design |
| 2.2 | Replacement design and permits | 20 | Apr 19 | May 14 | 2.1 | Design, project manager |
| 3.1 | Bid documents | 15 | Mar 8 | Mar 26 | 1.1 | Design, project manager |
| 3.2 | Advertise and receive bids | 20 | Mar 29 | Apr 23 | 3.1 | Project manager |
| 3.3 | Award and execute contract | 10 | Apr 26 | May 7 | 3.2, 1.2 | Project manager, finance |
| 4.1 | Notice letters and first community meeting | 10 | Mar 8 | Mar 19 | 1.1 | Outreach, project manager, printing |
| 4.2 | Access agreement campaign | 60 | Mar 22 | Jun 14 | 4.1 | Outreach, project manager, printing |
| 5.1 | Contractor mobilization | 5 | May 17 | May 21 | 3.3, 2.2 | Project manager |
| 5.2 | Replacement, Block A (140 lines) | 18 | Jun 15 | Jul 12 | 5.1, 4.2 | Replacement contractor, project manager, design |
| 5.3 | Replacement, Block B (140 lines) | 18 | Jul 13 | Aug 5 | 5.2 | Replacement contractor, project manager, design |
| 5.4 | Replacement, Block C (140 lines) | 18 | Aug 6 | Aug 31 | 5.3 | Replacement contractor, project manager, design |
| 5.5 | Restoration, Block A | 18 | Jun 23 | Jul 19 | 5.2 start + 5 days | Restoration contractor |
| 5.6 | Restoration, Block B | 18 | Jul 20 | Aug 12 | 5.3 start + 5 days | Restoration contractor |
| 5.7 | Restoration, Block C | 18 | Aug 13 | Sep 8 | 5.4 start + 5 days | Restoration contractor |
| 5.8 | Filter distribution | 54 | Jun 15 | Aug 31 | 5.2 start | Outreach, filters |
| 6.1 | Follow-up tap sampling (100 homes) | 35 | Sep 15 | Nov 2 | 5.2 + 45 days | Lab staff, outreach, laboratory analysis |
| 6.2 | Sampling report | 8 | Nov 3 | Nov 12 | 6.1 | Lab staff, project manager |
| 7.1 | Service line inventory update | 10 | Sep 9 | Sep 22 | 5.7 | Design |
| 8.1 | Closeout report and lessons for Phase 2 | 8 | Nov 15 | Nov 24 | 6.2, 7.1 | Project manager and all leads |
| 8.2 | Sponsor acceptance (milestone) | 0 | Nov 29 | Nov 29 | 8.1 | Project manager |
All dates fall in 2027. Holidays removed from the calendar are Memorial Day, Juneteenth (observed June 18), Independence Day (observed July 5), Labor Day and the Thanksgiving Thursday and Friday.
5. Cost Baseline by Summary Task
| Summary task | Cost |
|---|---|
| 1. Initiation | $6,014 |
| 2. Design and locate | $208,450 |
| 3. Procurement | $7,090 |
| 4. Customer outreach | $36,970 |
| 5. Construction, restoration and filters | $4,657,860 |
| 6. Sampling | $9,462 |
| 7. Inventory update | $3,400 |
| 8. Closeout | $6,434 |
| Baseline total | $4,935,680 |
| Contingency reserve (outside baseline) | $364,320 |
| Approved budget | $5,300,000 |
6. Critical Path and Float
Microsoft Project's critical path runs from the kickoff through the notice letters, the access agreement campaign, Block A, the follow-up sampling and its report to closeout and acceptance. Construction of Blocks B and C is not on it. Because sampling in Block A homes must wait about three months after their replacement, those homes, not the last block, determine when the closeout can begin; the 100 sampled homes are visited in the order they were replaced, so each sample is drawn about three months after its replacement. Blocks B and C carry roughly seven weeks of float. The project's real bottleneck is a signature on an access agreement, not a crew in a trench. That finding confirms the ranking in Part 1's risk matrix, where owner refusal scored highest, and it tells the sponsor where extra outreach staff would shorten the project. Contractor mobilization also has about three weeks of float, so the task is set to start as late as possible and the notice to proceed will be issued in early June, which avoids paying for an idle crew.
Gray and Larson (2018) describe how resource limits can change a schedule computed from logic alone. The replacement contractor's two crews are the constrained resource here, and the three blocks are linked finish-to-start for that reason: running them in parallel would require crews the contract does not provide. Kolisch and Padman (2001), surveying deterministic scheduling models, treat the resource-constrained problem as a central one in the field, and it is the point at which this plan departs from a schedule drawn from logic alone.
7. Buffer and Milestones
The computed finish of November 29 sits 13 working days ahead of the December 17 completion date promised in Part 1. Rather than spreading that time across tasks as padding, the model holds it as a single project buffer at the end. Herroelen and Leus (2005) review approaches to scheduling under uncertainty, including the proactive use of buffers to protect a schedule against disruption, and an explicit buffer at the end is easier to monitor than hidden slack in every estimate. The buffer is reported to the sponsor each month as days remaining.
Four milestones carry Part 1's risk triggers into the schedule: an access agreement checkpoint on May 3, when fewer than 80 percent signed would trigger the contingency; a weekly production check during each construction block, with two consecutive weeks under 35 lines triggering a third crew; a frost-risk review on October 15, now largely moot because construction ends on August 31; and the sampling report on November 12, when any result above 10 micrograms per liter would trigger repeat flushing and testing at that home.
References
Gray, C. F., & Larson, E. W. (2018). Project management: The managerial process (7th ed.). McGraw-Hill Education.
Herroelen, W., & Leus, R. (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 165(2), 289-306. https://doi.org/10.1016/j.ejor.2004.04.002
Kolisch, R., & Padman, R. (2001). An integrated survey of deterministic project scheduling. Omega, 29(3), 249-272. https://doi.org/10.1016/S0305-0483(00)00046-3
U.S. Environmental Protection Agency. (2024). National primary drinking water regulations for lead and copper: Improvements (LCRI) (89 FR 86418). Federal Register. https://www.federalregister.gov/d/2024-23549
What the BUSI 681 Week 8 instructions ask
The Project Model's second part closes BUSI 681 in Module/Week 8, the week of Gray and Larson's chapter 16, an introduction to agile project management, alongside the Forum 4 group reply and Quiz 8. The guide asks that Part 2 be created using Microsoft Project and that it include a detailed description of the project, a list of its principal deliverables and a breakdown of every necessary task with project dates, costs and resources. Part 2 counts for 150 points, matching the weight given to Part 1. Students keep the topic, scope and budget from Part 1, so the schedule's work breakdown, resource assignments and cost totals must match the proposal, responsibility matrix and risk responses submitted two weeks earlier.
How this BUSI 681 Week 8 example is built
The plan starts with a project description of about 250 words that restates purpose, scope and constraints from Part 1. Next comes a list of nine principal deliverables. The resource sheet follows as a table with rates and totals, and then the task breakdown, 22 tasks under eight summary groups, each with duration, start, finish, predecessors and resources, as Microsoft Project's Gantt view would export them. A cost table rolls the tasks up by summary group. Three closing sections explain the critical path, the buffer and the milestones that carry Part 1's risk triggers. Herroelen and Leus's survey of scheduling under uncertainty supports the decision to keep the buffer at the end of the project.
BUSI 681 Week 8 grading rubric: where the points go
Scoring for Part 2 rests on whether the Microsoft Project model is complete, realistic and consistent with Part 1. Graders look for a description that tells a reader what the project is and why it exists, deliverables that are tangible outputs rather than activities, a task breakdown detailed enough to manage with logical dependencies and no orphan tasks, durations and dates that respect working calendars, and resources assigned with rates so the plan produces a cost baseline. A model that finds its own critical path and explains it, shows where float sits and ties milestones to the risks named in Part 1 demonstrates the course's scheduling chapters in practice, not just the software.
BUSI 681 Week 8 help: mistakes that cost points
Typing tasks into Microsoft Project without linking them is the usual Part 2 error; the Gantt chart then looks complete while the dates mean nothing. Link every task to a predecessor and a successor except the start and the finish. Set the project calendar first, with weekends and holidays, before entering durations. Enter resources with rates on the resource sheet and assign them, rather than typing costs by hand, so the totals are traceable. Check the critical path view and explain it in prose, since the grader cannot ask you why a date falls where it does. Compare the cost total with the Part 1 budget and account for any difference. Export or screenshot the Gantt view legibly.
Related BUSI 681 sample papers
Other BUSI 681 weeks
- BUSI 681 Week 1: Forum 1: Crashing a Late Project
- BUSI 681 Week 2: Forum 1 Part 2: Leading a Crash
- BUSI 681 Week 3: Forum 2: Building a Split Team
- BUSI 681 Week 4: Forum 2 Reply: Outsourced Teams
- BUSI 681 Week 5: Forum 3: Earned Value as Warning
- BUSI 681 Week 6: Project Model Part 1: Lead Lines
- BUSI 681 Week 7: Forum 4: An Offshore Model Team
More MBA sample papers
- BUSI 644 Week 8: Faith Integration Group Essay
- BUSI 645 Week 8: Forum 4: Pay for Remote Workers
- BUSI 650 Week 8: Final Integrative Learning Project
- BUSI 680 Week 8: Forum 4 Reply: Shared Resources
BUSI 681 Week 8 questions, answered
What is the BUSI 681 Project Model Part 2?
The 150-point Module/Week 8 case study that rebuilds the student's Part 1 project in Microsoft Project, with a detailed description, principal deliverables and a breakdown of tasks, dates, costs and resources.
Where can I find a free BUSI 681 Week 8 sample paper?
This page carries a full BUSI 681 Week 8 Project Model Part 2, a 22-task Microsoft Project schedule for replacing 420 lead service lines with dates, a resource sheet and a cost baseline.
How do you find the critical path in Microsoft Project?
Link every task with its dependencies, then turn on the critical path display in the Gantt Chart view; tasks with zero total float are shown as critical, and their chain sets the finish date.
Does Part 2 of the BUSI 681 project model have to match Part 1?
Yes. The guide treats the two parts as one project model, so the scope, deliverables, roles and budget from Part 1's proposal and matrices should carry into the Microsoft Project schedule.
What does chapter 16 of Gray and Larson cover?
An introduction to agile project management, including how iterative, incremental methods such as Scrum differ from traditional plan-driven management and when each approach fits a project.
Use it as a model, or ask for your own
This paper is an original model written by our desk for study. It is not a submitted student paper and not an official Liberty University document. Read it for structure and reasoning, then write your own to the instructions in your Canvas course. If you want a version built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.