Here is the BUSI 681 Week 8 sample for Part 2 of the Project Model case study, the Microsoft Project build of the lead service line replacement planned in Part 1. A composite utility replaces 420 lead lines in one neighborhood, and the schedule turns Part 1's work packages into 22 tasks with durations, dependencies, dates and named resources. Start is March 1, 2027; the computed finish is November 29, which leaves 13 working days of buffer before the December 17 date promised to the sponsor. Costs come from a resource sheet of five internal roles and six cost-based resources, totaling $4,935,680 against a $5.30 million budget, and the critical path runs through the access agreement campaign rather than construction. Liberty University BUSI 681 grades this closing MBA case at 150 points.

CourseBUSI 681 Advanced Project Management II (BUSI681)
Module/Week8
AssignmentCase Study: Project Model Part 2
Paper typeProject model, part 2 of 2 (Microsoft Project plan)
Lengthabout 837 words, 3 double-spaced pages plus title page and references. Course guide: the second half of the project model, built in Microsoft Project, with a detailed project description, a list of principal deliverables and a breakdown of all necessary tasks with dates, costs and resources
FormatAPA 7 student paper
Points150
SchoolLiberty University Online
ProgramMBA
Where it sitsModule/Week 8 in Liberty's published BUSI 681 course guide; current sections can differ
UpdatedOctober 2026

Free sample paper for BUSI 681 Week 8

1

Maple Hill Lead Service Line Replacement, Phase 1: Microsoft Project Schedule with Deliverables, Task Breakdown, Dates, Costs and Resources

 

[Student Name]

School of Business, Liberty University

BUSI 681: Advanced Project Management II

Case Study: Project Model Part 2

[Instructor Name]

[Date]

 

The utility, the neighborhood, the dates and every cost and hour in the schedule are composites continuing Part 1 and were computed for this sample; the federal rule, the textbook and the research cited are real, and the required contents follow Liberty's public course guide for BUSI 681.

Why this part earns its pointsThe description restates purpose and limits before any dates appear, because a schedule only makes sense against the scope it delivers.
2

Maple Hill Lead Service Line Replacement, Phase 1: Microsoft Project Schedule with Deliverables, Task Breakdown, Dates, Costs and Resources

1. Project Description

Phase 1 of Riverbend Water's lead service line replacement program removes all 420 known lead service lines in the Maple Hill neighborhood, putting copper in place of the public and the private sections of each line alike, from the main to the meter. Full replacement is the point of the project: research on partial replacements found that cutting out only part of a lead line can raise lead release in household plumbing in the short term, and the federal Lead and Copper Rule Improvements generally require systems to remove lead service lines in full over the coming decade (U.S. Environmental Protection Agency [EPA], 2024).

The schedule runs from March 1, 2027, to a computed finish of November 29, 2027, using a calendar of five working days a week with six federal holidays removed. The work has four stages. Preparation covers the charter, the state loan, field verification of each line and the design and permits. Procurement selects a replacement contractor through competitive bidding. Customer outreach secures signed access agreements from property owners. Construction then replaces lines in three blocks of 140, followed by restoration, filter distribution, follow-up sampling, the inventory update and closeout. The budget is $5.30 million, and the plan's resource-loaded cost baseline is $4,935,680, leaving a contingency reserve of $364,320, about 7 percent of the budget, held outside the baseline under the sponsor's control. Excluded from the project are household plumbing beyond the meter, water main replacement and the other eight neighborhoods.

2. Principal Deliverables

  • 1. Approved project charter and executed state loan agreement.
  • 2. Field-verified material record for each of the 420 addresses.
  • 3. Stamped replacement design and street-opening permits.
  • 4. Executed unit-price construction contract.
  • 5. Signed access agreements from property owners.
  • 6. 420 full replacements, each with before and after photographs and a completion form.
  • 7. Restored sidewalks, driveways and lawns, inspected within 14 days of each replacement.
  • 8. Filters and six months of cartridges delivered to every household, and a sampling report covering 100 homes.
  • 9. Updated service line inventory and a closeout report with cost per line and lessons for Phase 2.
Why this part earns its pointsThe resource sheet carries rates and unit costs, so every dollar in the baseline traces to an assignment rather than a typed number.
3

3. Resource Sheet

ResourceTypeRate or unit costUnits or hoursTotal
Project managerWork$75 per hour640 hours$48,000
Engineering designWork$85 per hour352 hours$29,920
Customer outreach staffWork$48 per hour580 hours$27,840
Water quality lab staffWork$60 per hour60 hours$3,600
Finance analystWork$60 per hour32 hours$1,920
Locate contractorCost$450 per address420$189,000
Replacement contractorCost$9,800 per line420$4,116,000
Restoration contractorCost$1,100 per line420$462,000
Filters and cartridgesMaterial$95 per household420$39,900
Printing, mailing and meeting costsCostLump sums2$13,000
Laboratory analysisCost$45 per sample100$4,500
Total$4,935,680

Construction and restoration together cost $10,900 per line, under the $11,500 ceiling set as a success criterion in Part 1.

4. Task Breakdown

IDTaskDaysStartFinishPredecessorsResources
1.1Charter approval and kickoff5Mar 1Mar 5noneProject manager, design, outreach, finance
1.2Loan agreement executed20Mar 8Apr 21.1Finance, project manager
2.1Field verification of 420 service lines30Mar 8Apr 161.1Locate contractor, design
2.2Replacement design and permits20Apr 19May 142.1Design, project manager
3.1Bid documents15Mar 8Mar 261.1Design, project manager
3.2Advertise and receive bids20Mar 29Apr 233.1Project manager
3.3Award and execute contract10Apr 26May 73.2, 1.2Project manager, finance
4.1Notice letters and first community meeting10Mar 8Mar 191.1Outreach, project manager, printing
4.2Access agreement campaign60Mar 22Jun 144.1Outreach, project manager, printing
5.1Contractor mobilization5May 17May 213.3, 2.2Project manager
5.2Replacement, Block A (140 lines)18Jun 15Jul 125.1, 4.2Replacement contractor, project manager, design
5.3Replacement, Block B (140 lines)18Jul 13Aug 55.2Replacement contractor, project manager, design
5.4Replacement, Block C (140 lines)18Aug 6Aug 315.3Replacement contractor, project manager, design
5.5Restoration, Block A18Jun 23Jul 195.2 start + 5 daysRestoration contractor
5.6Restoration, Block B18Jul 20Aug 125.3 start + 5 daysRestoration contractor
5.7Restoration, Block C18Aug 13Sep 85.4 start + 5 daysRestoration contractor
5.8Filter distribution54Jun 15Aug 315.2 startOutreach, filters
6.1Follow-up tap sampling (100 homes)35Sep 15Nov 25.2 + 45 daysLab staff, outreach, laboratory analysis
6.2Sampling report8Nov 3Nov 126.1Lab staff, project manager
7.1Service line inventory update10Sep 9Sep 225.7Design
8.1Closeout report and lessons for Phase 28Nov 15Nov 246.2, 7.1Project manager and all leads
8.2Sponsor acceptance (milestone)0Nov 29Nov 298.1Project manager

All dates fall in 2027. Holidays removed from the calendar are Memorial Day, Juneteenth (observed June 18), Independence Day (observed July 5), Labor Day and the Thanksgiving Thursday and Friday.

5. Cost Baseline by Summary Task

Summary taskCost
1. Initiation$6,014
2. Design and locate$208,450
3. Procurement$7,090
4. Customer outreach$36,970
5. Construction, restoration and filters$4,657,860
6. Sampling$9,462
7. Inventory update$3,400
8. Closeout$6,434
Baseline total$4,935,680
Contingency reserve (outside baseline)$364,320
Approved budget$5,300,000
Why this part earns its pointsThe critical path discussion is where the model shows judgment, because the software finds the path but cannot say what it means.
4

6. Critical Path and Float

Microsoft Project's critical path runs from the kickoff through the notice letters, the access agreement campaign, Block A, the follow-up sampling and its report to closeout and acceptance. Construction of Blocks B and C is not on it. Because sampling in Block A homes must wait about three months after their replacement, those homes, not the last block, determine when the closeout can begin; the 100 sampled homes are visited in the order they were replaced, so each sample is drawn about three months after its replacement. Blocks B and C carry roughly seven weeks of float. The project's real bottleneck is a signature on an access agreement, not a crew in a trench. That finding confirms the ranking in Part 1's risk matrix, where owner refusal scored highest, and it tells the sponsor where extra outreach staff would shorten the project. Contractor mobilization also has about three weeks of float, so the task is set to start as late as possible and the notice to proceed will be issued in early June, which avoids paying for an idle crew.

Gray and Larson (2018) describe how resource limits can change a schedule computed from logic alone. The replacement contractor's two crews are the constrained resource here, and the three blocks are linked finish-to-start for that reason: running them in parallel would require crews the contract does not provide. Kolisch and Padman (2001), surveying deterministic scheduling models, treat the resource-constrained problem as a central one in the field, and it is the point at which this plan departs from a schedule drawn from logic alone.

7. Buffer and Milestones

The computed finish of November 29 sits 13 working days ahead of the December 17 completion date promised in Part 1. Rather than spreading that time across tasks as padding, the model holds it as a single project buffer at the end. Herroelen and Leus (2005) review approaches to scheduling under uncertainty, including the proactive use of buffers to protect a schedule against disruption, and an explicit buffer at the end is easier to monitor than hidden slack in every estimate. The buffer is reported to the sponsor each month as days remaining.

Four milestones carry Part 1's risk triggers into the schedule: an access agreement checkpoint on May 3, when fewer than 80 percent signed would trigger the contingency; a weekly production check during each construction block, with two consecutive weeks under 35 lines triggering a third crew; a frost-risk review on October 15, now largely moot because construction ends on August 31; and the sampling report on November 12, when any result above 10 micrograms per liter would trigger repeat flushing and testing at that home.

5

References

Gray, C. F., & Larson, E. W. (2018). Project management: The managerial process (7th ed.). McGraw-Hill Education.

Herroelen, W., & Leus, R. (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal of Operational Research, 165(2), 289-306. https://doi.org/10.1016/j.ejor.2004.04.002

Kolisch, R., & Padman, R. (2001). An integrated survey of deterministic project scheduling. Omega, 29(3), 249-272. https://doi.org/10.1016/S0305-0483(00)00046-3

U.S. Environmental Protection Agency. (2024). National primary drinking water regulations for lead and copper: Improvements (LCRI) (89 FR 86418). Federal Register. https://www.federalregister.gov/d/2024-23549

What the BUSI 681 Week 8 instructions ask

The Project Model's second part closes BUSI 681 in Module/Week 8, the week of Gray and Larson's chapter 16, an introduction to agile project management, alongside the Forum 4 group reply and Quiz 8. The guide asks that Part 2 be created using Microsoft Project and that it include a detailed description of the project, a list of its principal deliverables and a breakdown of every necessary task with project dates, costs and resources. Part 2 counts for 150 points, matching the weight given to Part 1. Students keep the topic, scope and budget from Part 1, so the schedule's work breakdown, resource assignments and cost totals must match the proposal, responsibility matrix and risk responses submitted two weeks earlier.

How this BUSI 681 Week 8 example is built

The plan starts with a project description of about 250 words that restates purpose, scope and constraints from Part 1. Next comes a list of nine principal deliverables. The resource sheet follows as a table with rates and totals, and then the task breakdown, 22 tasks under eight summary groups, each with duration, start, finish, predecessors and resources, as Microsoft Project's Gantt view would export them. A cost table rolls the tasks up by summary group. Three closing sections explain the critical path, the buffer and the milestones that carry Part 1's risk triggers. Herroelen and Leus's survey of scheduling under uncertainty supports the decision to keep the buffer at the end of the project.

BUSI 681 Week 8 grading rubric: where the points go

Scoring for Part 2 rests on whether the Microsoft Project model is complete, realistic and consistent with Part 1. Graders look for a description that tells a reader what the project is and why it exists, deliverables that are tangible outputs rather than activities, a task breakdown detailed enough to manage with logical dependencies and no orphan tasks, durations and dates that respect working calendars, and resources assigned with rates so the plan produces a cost baseline. A model that finds its own critical path and explains it, shows where float sits and ties milestones to the risks named in Part 1 demonstrates the course's scheduling chapters in practice, not just the software.

BUSI 681 Week 8 help: mistakes that cost points

Typing tasks into Microsoft Project without linking them is the usual Part 2 error; the Gantt chart then looks complete while the dates mean nothing. Link every task to a predecessor and a successor except the start and the finish. Set the project calendar first, with weekends and holidays, before entering durations. Enter resources with rates on the resource sheet and assign them, rather than typing costs by hand, so the totals are traceable. Check the critical path view and explain it in prose, since the grader cannot ask you why a date falls where it does. Compare the cost total with the Part 1 budget and account for any difference. Export or screenshot the Gantt view legibly.

Related BUSI 681 sample papers

Other BUSI 681 weeks

More MBA sample papers

BUSI 681 Week 8 questions, answered

What is the BUSI 681 Project Model Part 2?

The 150-point Module/Week 8 case study that rebuilds the student's Part 1 project in Microsoft Project, with a detailed description, principal deliverables and a breakdown of tasks, dates, costs and resources.

Where can I find a free BUSI 681 Week 8 sample paper?

This page carries a full BUSI 681 Week 8 Project Model Part 2, a 22-task Microsoft Project schedule for replacing 420 lead service lines with dates, a resource sheet and a cost baseline.

How do you find the critical path in Microsoft Project?

Link every task with its dependencies, then turn on the critical path display in the Gantt Chart view; tasks with zero total float are shown as critical, and their chain sets the finish date.

Does Part 2 of the BUSI 681 project model have to match Part 1?

Yes. The guide treats the two parts as one project model, so the scope, deliverables, roles and budget from Part 1's proposal and matrices should carry into the Microsoft Project schedule.

What does chapter 16 of Gray and Larson cover?

An introduction to agile project management, including how iterative, incremental methods such as Scrum differ from traditional plan-driven management and when each approach fits a project.

Use it as a model, or ask for your own

This paper is an original model written by our desk for study. It is not a submitted student paper and not an official Liberty University document. Read it for structure and reasoning, then write your own to the instructions in your Canvas course. If you want a version built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.