BUSI 681 Week 6 Case Study: Project Model Part 1 Example

Reviewed by Thomas Kerrigan, MBA, CPA · Liberty University · Updated

The BUSI 681 Week 6 sample below is Part 1 of the Project Model case study, laid out for a composite water utility's first phase of lead service line replacement: 420 homes in an older neighborhood, both the utility's and the owner's side of each line, at a planned cost of $5.3 million over ten months. The four parts the guide names appear in order. A proposal form defines purpose, scope, deliverables and success measures, a responsibility matrix assigns who does and who approves each work package, a risk assessment matrix rates seven risks and plans a response, trigger and owner for each, and a communication plan matches every stakeholder group to a message, channel and schedule. Liberty University BUSI 681 weights this MBA assignment at 150 points.

CourseBUSI 681 Advanced Project Management II (BUSI681)
Module/Week6
AssignmentCase Study: Project Model Part 1
Paper typeProject model, part 1 of 2
Lengthabout 1,041 words, 4 double-spaced pages plus title page and references. Course guide: the first half of a two-part project model on a topic of the student's choice, containing a Project Proposal Form, a Responsibility Matrix, a Risk Assessment Matrix and a Stakeholder Communication Plan
FormatAPA 7 student paper
Points150
SchoolLiberty University Online
ProgramMBA
Where it sitsModule/Week 6 in Liberty's published BUSI 681 course guide; current sections can differ
UpdatedOctober 2026

Free sample paper for BUSI 681 Week 6

1

Maple Hill Lead Service Line Replacement, Phase 1: Project Proposal, Responsibility Matrix, Risk Assessment Matrix and Stakeholder Communication Plan

 

[Student Name]

School of Business, Liberty University

BUSI 681: Advanced Project Management II

Case Study: Project Model Part 1

[Instructor Name]

[Date]

 

The utility, the Maple Hill neighborhood and every figure in the plan are composites built for this sample; the federal rule, the textbook and the research cited are real, and the four required parts follow Liberty's public course guide for BUSI 681.

Why this part earns its pointsThe orientation paragraph names the project and the reason for it in two sentences, so a reader can judge every later document against that purpose.
2

Maple Hill Lead Service Line Replacement, Phase 1: Project Proposal, Responsibility Matrix, Risk Assessment Matrix and Stakeholder Communication Plan

Orientation

Riverbend Water, a composite municipal utility serving about 160,000 people, completed its service line inventory and found 3,900 lead service lines, most of them in neighborhoods built before 1940. This model plans Phase 1 of their replacement: 420 lines in the Maple Hill neighborhood, chosen because it has the highest concentration of lead lines and the largest number of young children in the service area. The federal Lead and Copper Rule Improvements, published in October 2024, generally require systems to replace lead service lines within ten years, so Phase 1 is also the utility's test of the process it will repeat across eight more neighborhoods (U.S. Environmental Protection Agency [EPA], 2024).

1. Project Proposal Form

FieldEntry
Project titleMaple Hill Lead Service Line Replacement, Phase 1
SponsorDirector of Engineering, Riverbend Water
Project managerCapital Projects Manager
Planned start and finishMarch 1, 2027, to December 17, 2027
Budget$5.30 million, including a contingency reserve of about 7 percent
FundingState revolving fund loan with partial principal forgiveness, plus capital reserves
Customers420 households in Maple Hill and the utility's operations division

Purpose. The project removes every known lead service line in Maple Hill, from the water main to the meter inside each home, so residents no longer drink water that has passed through lead pipe. Gray and Larson (2018) describe the project scope statement as the definition of what the project is meant to produce for its customer, and the customer here is the household, not the utility's compliance office.

Objectives. Replace 420 lead service lines in full, both the utility-owned and the customer-owned sections, by December 17, 2027, within $5.30 million. Restore every excavated sidewalk, driveway and lawn within 14 days of the replacement. Deliver a lead-reducing pitcher filter and six months of cartridges to every household on the day of replacement, and collect a follow-up tap sample from at least 100 homes three to six months later.

Scope. Included are property owner outreach and signed access agreements, locating and excavation, full replacement using copper service pipe, meter setting relocation where needed, restoration, filter distribution, sampling and an updated inventory record for each address. Excluded are lead or galvanized plumbing inside the home beyond the meter, replacement of the water main itself and the other eight neighborhoods.

Deliverables. The project hands over signed access agreements, 420 finished replacements documented with photographs, restored yards and walks, filters in every home, a report on post-replacement sampling, a corrected inventory record for each address and a closing report that states the unit cost achieved and what Phase 2 should do differently.

Success criteria. All 420 lines replaced in full, with no partial replacements; cost per line no more than $11,500 for construction and restoration; no lost-time injuries; and post-replacement sampling showing lead below the action level of 10 micrograms per liter in at least 95 percent of samples.

Assumptions and constraints. The plan assumes that at least 95 percent of owners will sign access agreements and that the contractor can complete eight replacements a day across two crews. Construction stops for frozen ground and cannot take a main out of service during the summer peak.

Why this part earns its pointsThe responsibility matrix gives each work package exactly one accountable role, which is where most role confusion on utility projects begins.
3

2. Responsibility Matrix

In the chart, R marks the role that performs a package, A the single role that signs it off, C a role whose advice is sought and I a role kept up to date.

Work packageProject managerEngineering designContractorCustomer outreachWater quality labFinance
Access agreementsAIIRII
Locate and designARCIII
Contractor procurementACIIIR
Excavation and replacementACRIII
Site restorationAIRCII
Filter distributionAICRCI
Follow-up samplingIIICR, AI
Inventory updateARCIII
Funding draws and reportingCIIIIR, A
Closeout reportR, ACCCCC

The matrix settles three decisions that caused trouble on earlier capital projects. First, customer outreach, not the contractor, owns access agreements, because residents trust the utility's own staff more than a crew at the door. Second, the water quality lab is accountable for its own sampling results, so the project manager cannot be seen to influence them. Third, finance owns funding draws, since the state loan requires documentation that only finance prepares. Gray and Larson (2018) recommend building the responsibility matrix with the people named in it, and each lead reviewed this chart before it was final.

Why this part earns its pointsThe paragraph after the matrix explains how the scores will be used, which keeps a simple chart from being treated as more precise than it is.
4

3. Risk Assessment Matrix

Likelihood (L) and impact (I) are rated from 1 (very low) to 5 (very high); the score is their product.

Risk eventLIScoreResponseContingency planTriggerOwner
Owners refuse or delay access agreements4416Mitigate: door-to-door visits, translated materials, evening sign-up sessionsResequence crews to signed blocks; escalate holdouts to the sponsorFewer than 80 percent signed by May 3Customer outreach lead
Short-term lead spike after replacement3515Mitigate: flushing protocol and filters on the day of workRepeat flushing and free lab test for the householdAny post-replacement sample above 10 micrograms per literWater quality lab
Contractor falls behind eight lines a day3412Mitigate: weekly production review written into the contractAdd a third crew under the contract's unit-price optionTwo consecutive weeks under 35 linesProject manager
Unknown lead found beyond the inventory339Accept: budget allowance for 30 added linesAdd the lines to Phase 1 if the reserve allows; otherwise to Phase 2Excavation finds lead at an address listed as non-leadEngineering design
Copper pipe price increase236Transfer: fixed unit prices for materials in the contractDraw on contingency reserveSupplier notice of increase over 10 percentFinance
Crew injury in excavation2510Avoid and mitigate: trench safety plan and daily inspectionStop work at the site; incident review before restartAny recordable incidentContractor
Early freeze ends the season248Accept: schedule finishes four weeks before average first frostCarry unfinished lines into spring 2028 with the sponsor's approvalForecast of frozen ground before November 15Project manager

The scores rank risks for attention; they do not measure them. Cox (2008) showed that risk matrices can rate quantitatively different risks the same and can even give a higher rating to a smaller risk, so the team uses the scores to decide where to look first and then discusses each high-impact risk separately. For this reason the crew injury risk, which scores only 10, has an avoidance response and a stop-work contingency. A trench collapse is unacceptable at any likelihood, whatever its score in the matrix. Gray and Larson (2018) describe the contingency plan and its trigger point as the part of risk management that turns a list into a decision rule, and every row above has one.

4. Stakeholder Communication Plan

StakeholderInformation neededMethodFrequencySender
Maple Hill householdsWhy the work is needed, date of their replacement, what to expect, flushing and filter useMailed letter, door hanger, text message, community meetingLetter 60 days before; door hanger 7 days before; text 1 day before; meetings in March and JuneCustomer outreach lead
Property owners who rent their homesAccess agreement, no cost to them, tenant noticeLetter and phone callAt project launch and until signedCustomer outreach lead
City council and utility boardProgress, cost per line, risksDashboard and briefingMonthlySponsor and project manager
State drinking water programLines replaced, sampling results, inventory updatesRequired reportsAs the rule and loan requireWater quality lab and finance
ContractorWeekly schedule, signed addresses, design changesCoordination meeting and shared site listWeeklyProject manager
Utility customer service staffAnswers to common questions, schedule by streetBriefing sheet and call scriptEvery two weeksCustomer outreach lead
Local mediaProject purpose, traffic impactsNews releaseAt launch, midpoint and completionUtility communications office

The household message was shaped by research on partial replacements. Trueman et al. (2016) found that full replacement reduced lead levels within days and lowered them throughout the sample profile within a month, while cutting out only part of a line left the first liters drawn from the tap carrying over twice as much lead in the weeks that followed. Deshommes et al. (2017) observed erratic spikes in particulate lead for up to 18 months after partial replacements. For that reason, the letters explain plainly why the utility needs to replace the owner's portion of the line and why the flushing instructions and filter matter in the first months. Pieper et al. (2017) traced how lead release at one Flint home rose after corrosion control was interrupted, a reminder that residents in older neighborhoods have good reason to want straight answers about their water. Eskerod et al. (2015) describe stakeholder management in projects as an ongoing relationship, not a single notice, which is why the plan schedules contact before, during and after each replacement.

5. Carrying the Model into Part 2

Part 2 will rebuild this project in Microsoft Project, so the documents above were written to translate directly. The ten work packages in the responsibility matrix become summary tasks, and the roles in its columns become the resource sheet, with the contractor's two crews entered as a work resource paid by the line rather than by the hour. The $5.30 million budget will be loaded as costs on those tasks, with the contingency reserve of roughly $364,000 held outside the baseline so that it can be drawn only with the sponsor's approval. Each risk's trigger date becomes a milestone, so the schedule itself warns the team when a contingency decision is due. Finally, the communication plan's letters, door hangers and meetings will appear as tasks tied to the replacement sequence, because notices sent late would break the promise made to residents in this plan.

5

References

Cox, L. A., Jr. (2008). What's wrong with risk matrices? Risk Analysis, 28(2), 497-512. https://doi.org/10.1111/j.1539-6924.2008.01030.x

Deshommes, E., Laroche, L., Deveau, D., Nour, S., & Prévost, M. (2017). Short- and long-term lead release after partial lead service line replacements in a metropolitan water distribution system. Environmental Science & Technology, 51(17), 9507-9515. https://doi.org/10.1021/acs.est.7b01720

Eskerod, P., Huemann, M., & Savage, G. (2015). Project stakeholder management: Past and present. Project Management Journal, 46(6), 6-14. https://doi.org/10.1002/pmj.21555

Gray, C. F., & Larson, E. W. (2018). Project management: The managerial process (7th ed.). McGraw-Hill Education.

Pieper, K. J., Tang, M., & Edwards, M. A. (2017). Flint water crisis caused by interrupted corrosion control: Investigating "ground zero" home. Environmental Science & Technology, 51(4), 2007-2014. https://doi.org/10.1021/acs.est.6b04034

Trueman, B. F., Camara, E., & Gagnon, G. A. (2016). Evaluating the effects of full and partial lead service line replacement on lead levels in drinking water. Environmental Science & Technology, 50(14), 7389-7396. https://doi.org/10.1021/acs.est.6b01912

U.S. Environmental Protection Agency. (2024). National primary drinking water regulations for lead and copper: Improvements (LCRI) (89 FR 86418). Federal Register. https://www.federalregister.gov/d/2024-23549

What the BUSI 681 Week 6 instructions ask

Part 1 of the Project Model reaches the instructor in BUSI 681's sixth module, while the class reads chapter 14 on closing projects, with the Forum 3 group reply and Quiz 6 due alongside it. The guide asks each student to model a project on a topic of his or her own choosing and to deliver, in this first part, four named documents: a Project Proposal Form, a Responsibility Matrix, a Risk Assessment Matrix and a Stakeholder Communication Plan. The topic was named back in Module/Week 2 as an ungraded submission. Part 1 earns 150 points, and Part 2 builds the same project in Microsoft Project for the final module, so the choices made here become the plan's tasks, owners and costs.

How this BUSI 681 Week 6 example is built

The model is organized as four labeled documents behind a short orientation paragraph. The proposal form uses a table for the fixed facts, sponsor, dates, budget and funding, then prose for purpose, objectives, scope boundaries, deliverables and success criteria. A RACI chart follows, with one row per work package and one column per role, and a paragraph on the decisions it settles. The risk assessment matrix rates seven risks on likelihood and impact from 1 to 5, multiplies them and gives each a response, contingency, trigger and owner; a paragraph drawn from Cox's critique explains how the scores are used. The communication plan closes with a table for each audience and a note on research about partial replacements that shaped the message.

BUSI 681 Week 6 grading rubric: where the points go

The 150 points go to completeness and quality across the four required documents. The proposal must define a project with a clear purpose, measurable objectives, explicit scope boundaries, deliverables and success criteria, the elements of a scope statement in the textbook's terms. The responsibility matrix should cover every major work package and give each one exactly one accountable party. Graders check that the risk matrix rates likelihood and impact consistently and that responses are specific, with triggers and owners, and that the communication plan names each stakeholder's information needs, the channel, the frequency and who sends it. Because Part 2 continues the model, internal consistency counts: the same work packages, roles and budget should appear across all four parts.

BUSI 681 Week 6 help: mistakes that cost points

Students who pick an enormous topic, such as building a hospital, find that Part 2's task list in Microsoft Project becomes unmanageable; choose a project you can break into 30 to 60 tasks. Write measurable objectives with numbers and dates rather than aims such as improving service. In the RACI chart, give each row one A, and check that no column is empty or full. Avoid generic risks such as bad weather without saying what it would delay. Every risk needs a trigger that tells you the response is due. Link the communication plan to the risks, since many risks are managed by telling the right people early. Keep the budget and dates you set here, because Part 2 must match them.

Related BUSI 681 sample papers

Other BUSI 681 weeks

More MBA sample papers

BUSI 681 Week 6 questions, answered

What is the BUSI 681 Project Model Part 1?

The first half of the course's two-part case study, due in Module/Week 6 for 150 points: a Project Proposal Form, a Responsibility Matrix, a Risk Assessment Matrix and a Stakeholder Communication Plan for a project the student chooses.

Where can I find a free BUSI 681 Week 6 sample paper?

A complete BUSI 681 Week 6 Project Model Part 1 is on this page, planning a utility's replacement of 420 lead service lines with all four required documents.

What is a responsibility matrix in project management?

A chart, often called a RACI matrix, that lists work packages against the people or groups involved and marks, for every package, which role does the work, which single role answers for it, whose advice is needed and who only hears about it.

What goes in a risk assessment matrix?

Each risk event with its likelihood and impact ratings, a combined score, the planned response, a contingency plan, the trigger that sets the contingency in motion and the person who owns the risk.

What is due in BUSI 681 Module/Week 8?

Part 2 of the project model, the same project built in Microsoft Project with a description, principal deliverables, tasks, dates, costs and resources, worth 150 points, with the last group reply and Quiz 8.

Use it as a model, or ask for your own

This paper is an original model written by our desk for study. It is not a submitted student paper and not an official Liberty University document. Read it for structure and reasoning, then write your own to the instructions in your Canvas course. If you want a version built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.