BUSI 313 Week 7 Project Section 2 Example

Reviewed by Thomas Kerrigan, MBA, CPA · Liberty University · Updated

This BUSI 313 Week 7 sample shows the second section of the course project, continuing the composite clinic relocation planned in Section 1. At the week 10 status date, it compares the clinic's actual progress and spending with the Section 1 baseline through earned value. It interprets what the numbers mean, forecasts the cost at completion, proposes a recovery plan that protects the move date by shortening a critical activity, and lays out how the project will close, from final acceptance to a lessons-learned review. Business administration students in Liberty University BUSI 313 submit this clinic status and closeout section for 150 points.

CourseBUSI 313 Foundations of Project Management (BUSI313)
Module/Week7
AssignmentProject Section 2
Paper typeProject status and closure plan section
Lengthabout 642 words, 2 double-spaced pages plus title page and references. Course guide: a clearly marked and organized Word file presenting the second section of the course project, built on the chapters on progress and performance measurement and project closure
FormatAPA 7 student paper
Points150
SchoolLiberty University Online
ProgramBS in Business Administration
Where it sitsModule/Week 7 in Liberty's published BUSI 313 course guide; current sections can differ
UpdatedOctober 2026

Free sample paper for BUSI 313 Week 7

1

Eastside Clinic Relocation: Week 10 Earned Value Status Report, Recovery Plan and Closure Plan

 

[Student Name]

School of Business, Liberty University

BUSI 313: Foundations of Project Management

Project Section 2

[Instructor Name]

[Date]

 

The clinic, its figures and its status are a composite continuing Section 1; the section's parts follow the progress measurement and closure chapters assigned before it, and the textbook and research cited are real.

Why this part earns its pointsThe summary gives a sponsor the status in one paragraph before the detail.
2

Eastside Clinic Relocation: Week 10 Earned Value Status Report, Recovery Plan and Closure Plan

1. Status Summary

At the end of week 10, the relocation is about one week behind schedule and about 8 percent over budget on the work performed. Renovation, the critical activity, is 75 percent complete instead of the planned 87.5 percent because the contractor found deteriorated subfloor in two exam rooms. All other activities scheduled to date are complete. With the recovery action recommended below, the move date of week 18 can be held, and the forecast cost remains within the authorized budget including contingency.

2. Earned Value at Week 10

Planned value assumes each activity's cost is spent evenly across its scheduled weeks, following the early-start baseline from Section 1.

ActivityBudgetPlanned valuePercent completeEarned valueActual cost
A Lease and floor plan$4,000$4,000100%$4,000$4,200
B Network design$6,000$6,000100%$6,000$5,800
C Order furniture$1,500$1,500100%$1,500$1,500
D Renovation$120,000$105,00075%$90,000$98,000
I Patient notification$5,000$5,000100%$5,000$5,300
Total$136,500$121,500$106,500$114,800
  • Schedule variance: EV minus PV, $106,500 less $121,500, is negative $15,000.
  • Cost variance: EV minus AC, $106,500 less $114,800, is negative $8,300.
  • Schedule performance index: earned value over planned value, 106,500 over 121,500, gives 0.88.
  • Cost performance index: earned value over actual cost, 106,500 over 114,800, gives 0.93.
  • Estimate at completion: budget at completion of $266,000 divided by a CPI of 0.93 is about $286,700.

3. Interpretation

Read through Larson and Gray (2018), the two indexes say the clinic has finished only 88 cents of work for every planned dollar and paid a dollar for every 93 cents of work accomplished. Both indexes point to the same activity: renovation. The subfloor repair added labor and materials and slowed progress. The variance is not spread across the project; it sits almost entirely on the one activity the move date depends on. Because renovation is on the critical path, two weeks of work remain on an activity that was due to finish at the end of week 11, so the activity will now finish at the end of week 12, pushing every later critical activity back one week unless something changes.

Research supports acting now rather than waiting. Lipke et al. (2009) showed how statistical methods applied to the performance indexes can forecast final cost and duration with stated confidence, giving a manager an early and defensible warning instead of a hunch. The forecast cost of about $286,700 exceeds the direct budget of $266,000 by roughly $20,700 but remains within the authorized budget of $292,600, leaving about $5,900 of contingency.

Why this part earns its pointsThe recovery plan targets a critical activity, since time saved elsewhere would not move the finish date.
3

4. Recovery Plan

Two options were compared for recovering the lost week.

OptionActionTime recoveredAdded cost
1Overtime for the renovation crew to finish by week 111 week$9,500
2Add a second installation crew to cut furniture and equipment installation from 4 weeks to 31 week$4,500

Option 2 is recommended. Furniture installation is also critical, and it can be shortened at less than half the cost of overtime without asking an already strained renovation crew to work longer days. Under Option 2, installation runs from the end of week 12 to the end of week 15, staff training from 15 to 17 and the move in week 18. Network installation, which had one week of slack, now has none and becomes critical, so the IT vendor has been asked to confirm crew availability for weeks 13 to 15. With the $4,500, forecast cost rises to about $291,200, still within the authorized budget, and contingency would then be nearly exhausted, which the director has been informed of.

Why this part earns its pointsClosure is planned before the work ends, so lessons and sign-offs are not lost in the rush.
4

5. Closure Plan

  • Final acceptance: walkthrough with the clinic director and medical lead in week 18, using the acceptance criteria from the scope statement.
  • Contract closeout: confirm the contractor's punch list is complete, release retainage and close purchase orders.
  • Release of resources: return borrowed staff to normal duties and close the project budget.
  • Documentation: archive drawings, warranties, inspection approvals and the network configuration.
  • Lessons-learned review: a facilitated meeting within two weeks of go-live, with findings recorded in the clinic's project file.

6. Making the Review Count

Larson and Gray (2018) treat the project review as a key part of closure, but research shows organizations often fail to use what they learn. Williams (2008) found that while many organizations conduct reviews, few have effective ways to carry the lessons into future projects. The clinic will therefore assign the facilities manager to add one specific item from this review, the need to inspect subfloors before renovation estimates, to the checklist used for future building projects.

5

References

Larson, E. W., & Gray, C. F. (2018). Project management: The managerial process (7th ed.). McGraw-Hill Education.

Lipke, W., Zwikael, O., Henderson, K., & Anbari, F. (2009). Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes. International Journal of Project Management, 27(4), 400-407. https://doi.org/10.1016/j.ijproman.2008.02.009

Williams, T. (2008). How do organizations learn lessons from projects, and do they? IEEE Transactions on Engineering Management, 55(2), 248-266. https://doi.org/10.1109/TEM.2007.912920

What the BUSI 313 Week 7 instructions ask

Section 2 arrives in Module/Week 7, once the reading has covered outsourcing, measuring progress and closing projects. Worth 150 points, it is submitted like Section 1 as a clearly marked and organized Microsoft Word file, and the Forum 4 thread is due the same module/week. The section is meant to show the plan in motion: measuring a project's progress honestly against its baseline, explaining what the measures mean for the schedule and budget, deciding what to do, and preparing to close the project in an orderly way. It builds directly on Section 1's baseline. Earned value drives the analysis.

How this BUSI 313 Week 7 example is built

The section opens with a one-paragraph status summary a sponsor could read alone. A table shows the baseline and actual figures for each activity at week 10, followed by the earned value calculations with their formulas. An interpretation section explains why the project is behind and over budget and what the indexes predict. A recovery plan compares two options for regaining the lost week and recommends one with its cost. A closure plan lists the steps from final acceptance through the lessons-learned review, and a short section on research explains why the indexes and the review deserve attention. Tables are labeled throughout. The recovery options are shown side by side so the recommendation can be checked. A closing section explains how the lessons will actually be used.

BUSI 313 Week 7 grading rubric: where the points go

Section 2 is graded on the accuracy of its performance measurement, the quality of its interpretation and decisions, the completeness of its closure plan and the clarity of the Word document. Instructors check the earned value arithmetic, whether variances and indexes are interpreted correctly, whether the recovery plan addresses the critical path and whether the forecast and plan are consistent with Section 1's baseline. Unexplained ratios and recovery plans aimed at noncritical work both cost points. Professional formatting with labeled tables and clear headings is part of the score. A status summary written for the sponsor, separate from the calculations, shows the student can communicate performance as well as compute it. Labeled tables also help.

BUSI 313 Week 7 help: mistakes that cost points

Start from your Section 1 baseline and choose a status date. Build a table of planned value from the time-phased budget, then estimate percent complete honestly for each activity to get earned value. Record actual costs separately. Compute SV, CV, SPI and CPI, and explain each in plain words. Check whether the late activities are on the critical path before deciding what to do. Compare at least two recovery options with their costs. Finish with a closure plan that includes acceptance, contract closeout, staff release and a lessons-learned review. Show each formula with its numbers so a reader can verify the arithmetic. State clearly how much contingency remains after any recovery spending.

Related BUSI 313 sample papers

Other BUSI 313 weeks

More BS in Business Administration sample papers

BUSI 313 Week 7 questions, answered

What is BUSI 313 Project Section 2?

Section 2, worth 150 points in Module/Week 7, measures the project against its Section 1 baseline with earned value and lays out how it will close.

Where can I find a free BUSI 313 Week 7 sample paper?

The clinic relocation's week 10 status report, recovery options and closeout steps make up the full BUSI 313 Week 7 sample on this page.

What do SPI and CPI mean?

SPI compares work done with work scheduled, and CPI compares work done with money spent; either one under 1.0 is a warning, as the clinic's 0.88 and 0.93 show.

How do you forecast cost at completion with earned value?

For the clinic, $266,000 divided by a CPI of 0.93 gives about $286,700, a forecast that assumes spending efficiency stays where it has been.

What else is due in BUSI 313 Module/Week 7?

The final forum thread is due with the project section, and the reading covers outsourcing, performance measurement and closure. Replies follow in Module/Week 8.

Use it as a model, or ask for your own

This paper is an original model written by our desk for study. It is not a submitted student paper and not an official Liberty University document. Read it for structure and reasoning, then write your own to the instructions in your Canvas course. If you want a version built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.