BUSI 313 Week 3 Project Section 1 Example

Reviewed by Thomas Kerrigan, MBA, CPA · Liberty University · Updated

This BUSI 313 Week 3 sample shows the first section of the course project, a plan for relocating a composite community health clinic to a renovated building in eighteen weeks. Organized the way the assigned chapters build a plan, it states the project objective, sets out a scope statement with deliverables, milestones, exclusions and acceptance criteria, breaks the work into ten activities, estimates their durations and costs, and lays out a network schedule with early and late start times, slack and the critical path. A budget with a contingency reserve completes the section. Liberty University BUSI 313 awards up to 150 points for this business administration project section in Module/Week 3.

CourseBUSI 313 Foundations of Project Management (BUSI313)
Module/Week3
AssignmentProject Section 1
Paper typeProject plan section
Lengthabout 505 words, 2 double-spaced pages plus title page and references. Course guide: a clearly marked and organized Word file presenting the first section of the course project, built on the chapters on defining the project, estimating times and costs, and developing a project schedule
FormatAPA 7 student paper
Points150
SchoolLiberty University Online
ProgramBS in Business Administration
Where it sitsModule/Week 3 in Liberty's published BUSI 313 course guide; current sections can differ
UpdatedOctober 2026

Free sample paper for BUSI 313 Week 3

1

Relocating the Eastside Community Health Clinic: Project Definition, Estimates and Schedule

 

[Student Name]

School of Business, Liberty University

BUSI 313: Foundations of Project Management

Project Section 1

[Instructor Name]

[Date]

 

The clinic, its figures and its schedule are a composite; the section's parts follow the defining, estimating and scheduling chapters assigned before it, and the textbook and research cited are real.

Why this part earns its pointsThe objective puts scope, time and cost in one sentence, which the chapters recommend.
2

Relocating the Eastside Community Health Clinic: Project Definition, Estimates and Schedule

1. Project Objective

Relocate the Eastside Community Health Clinic to a renovated 8,000-square-foot building and resume full patient service within 18 weeks of project start, at a cost not to exceed $292,600, with no more than one day of closed clinic hours.

2. Scope Statement

Deliverables

  • Renovated building with eight exam rooms, a laboratory and a pharmacy window.
  • Working data network, phones and electronic health record access at every workstation.
  • Furniture and medical equipment installed and tested.
  • Occupancy and health department approvals.
  • Trained staff and informed patients.

Milestones

  • Lease signed and floor plan approved: end of week 3.
  • Renovation complete: end of week 11.
  • Inspections passed: end of week 13.
  • Move and go-live: end of week 18.

Technical Requirements

  • Exam rooms meet the state's clinic licensing standards for size and handwashing access.
  • Network supports the existing electronic health record system without new licenses.

Limits and Exclusions

  • The project does not include hiring new staff, changing clinic hours or replacing the electronic health record system.
  • Parking lot resurfacing is the landlord's responsibility and is outside the project.

Customer Review

  • The clinic director accepts each milestone in writing; the final walkthrough with the director and the medical lead confirms readiness before move day.
Why this part earns its pointsThe work breakdown, estimates and schedule share one activity list, so they can be checked against each other.
3

3. Work Breakdown and Estimates

Durations are most likely estimates from the facilities manager, contractor quotes and the clinic's 2019 expansion, used as a reference project. Larson and Gray (2018) recommend using past projects and expert judgment together, and research on optimism in estimates supports grounding them in comparable past work rather than in best-case plans (Flyvbjerg et al., 2002). Using the 2019 expansion as a benchmark is a way of taking the outside view, which corrects planners' habit of picturing only their own project's steps (Kahneman & Lovallo, 1993).

ActivityDescriptionOwnerDuration (weeks)Cost
AFinalize lease and floor planDirector3$4,000
BDesign network and phone systemIT lead2$6,000
COrder furniture and equipmentOffice manager1$1,500
DRenovate exam rooms, lab and pharmacyContractor8$120,000
EInstall cabling and networkIT vendor3$18,000
FReceive and install furniture and equipmentOffice manager4$92,000
GObtain occupancy and health inspectionsFacilities2$3,500
HTrain staff on new layout and systemsNurse manager2$9,000
INotify patients and update directoriesOffice manager4$5,000
JMove and go-liveDirector1$7,000

4. Network Schedule

Dependencies: B, C, D and I follow A; E follows B and D; F follows C and D; G follows D; H follows E and F; J follows G, H and I. The forward and backward passes give the following schedule, in weeks.

ActivityPredecessorsESEFLSLFSlack
Anone03030
BA3510127
CA3410117
DA3113110
EB, D111412151
FC, D111511150
GD111315174
HE, F151715170
IA37131710
JG, H, I171817180

The critical path is A, D, F, H, J, totaling 18 weeks. Every other activity has slack: network design and furniture ordering can each slip seven weeks, inspections four, and patient notification ten, which gives the project manager room to smooth workloads without moving the move date. Renovation is the activity the whole move depends on: every week it slips is a week the clinic opens late. Network installation has only one week of slack, so it is a near-critical activity that the project manager will watch closely.

Why this part earns its pointsThe reserve is sized from named risks instead of being added as a round number.
4

5. Budget and Reserve

Direct activity costs total $266,000. A contingency reserve of 10 percent, $26,600, covers identified risks such as renovation surprises in an older building, bringing the authorized budget to $292,600. The reserve is held by the project manager and released only with the director's approval, so that it is not absorbed silently into activity budgets.

6. Next Steps

This plan becomes the baseline for tracking progress. Section 2 will report status against it using earned value and will plan the project's closure. The schedule will be loaded into the clinic's project software with the baseline saved, and weekly status meetings will begin at the start of renovation.

5

References

Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002). Underestimating costs in public works projects: Error or lie? Journal of the American Planning Association, 68(3), 279-295. https://doi.org/10.1080/01944360208976273

Kahneman, D., & Lovallo, D. (1993). Timid choices and bold forecasts: A cognitive perspective on risk taking. Management Science, 39(1), 17-31. https://doi.org/10.1287/mnsc.39.1.17

Larson, E. W., & Gray, C. F. (2018). Project management: The managerial process (7th ed.). McGraw-Hill Education.

What the BUSI 313 Week 3 instructions ask

The first section of the BUSI 313 project is due in Module/Week 3, after students read Larson and Gray's chapters 4 to 6 on defining the project, estimating project times and costs, and developing a project schedule. At 150 points it ties Section 2 as the heaviest grade, and the guide wants it as a clearly labeled, well-ordered Word document. A second forum thread and one presentation also land here. Because Section 2 in Module/Week 7 builds on this plan, the estimates and schedule set here become the baseline against which the project's progress will later be measured.

How this BUSI 313 Week 3 example is built

The sample moves through the plan in the order the chapters teach it. A project objective states the result, deadline and budget in one sentence. In the scope section, the clinic's deliverables and four milestones sit beside licensing requirements, the parking lot exclusion and the director's sign-off. A work breakdown table assigns each activity an owner, a duration and a cost. The schedule table shows each activity's predecessors, early and late start and finish, and slack, identifying the critical path. A budget summary with a contingency reserve closes the section, and every table is labeled so a reader can follow the logic. Activity letters stay the same in every table, which lets a grader trace one task from scope to schedule.

BUSI 313 Week 3 grading rubric: where the points go

Project sections are graded on completeness, accuracy and organization: whether the plan defines the project clearly, whether estimates are reasonable and documented, whether the schedule's logic and calculations are correct and whether the document is clearly marked and easy to follow. Instructors check that the work breakdown, the estimates and the network agree with one another and that the critical path is computed correctly from the dependencies. A plan that lists tasks without durations or dependencies, or that miscalculates slack, loses points. Professional presentation in Word, with headings and labeled tables, is part of the grade. A short narrative explaining the critical path and the largest risks helps the grader see that the numbers have been understood, not just produced.

BUSI 313 Week 3 help: mistakes that cost points

Choose a project you understand well enough to describe in detail, such as an office move, an event or a system installation. Write the objective first, then a scope statement that says what is and is not included. Break the work into activities small enough to estimate, and record each estimate's basis. Draw the network on paper before building the table, and do the forward and backward passes carefully; check that the critical path has zero slack and adds up to the project duration. Add a contingency reserve and explain it. Label every table, and save the plan as your baseline for Section 2. Recheck slack values after any change to a duration or dependency.

Related BUSI 313 sample papers

Other BUSI 313 weeks

More BS in Business Administration sample papers

BUSI 313 Week 3 questions, answered

What is BUSI 313 Project Section 1?

The 150-point first section of the course project, due in Module/Week 3 as an organized Word file, applying the chapters on project definition, estimating and scheduling.

Where can I find a free BUSI 313 Week 3 sample paper?

This page shows a complete BUSI 313 Week 3 project section for a clinic relocation, with scope statement, estimates, network schedule and budget.

How do you find the critical path?

Do a forward pass to find each activity's earliest start and finish, a backward pass to find its latest start and finish, and then identify the chain of activities with zero slack.

What goes in a project scope statement?

Larson and Gray's scope checklist runs from the one-sentence objective through deliverables, milestones and technical requirements to what is excluded and how the client will sign off.

What else is due in BUSI 313 Module/Week 3?

A Forum 2 thread on estimating or scheduling is also due, alongside Larson and Gray's chapters 4 to 6. The thread needs two sources.

Use it as a model, or ask for your own

This paper is an original model written by our desk for study. It is not a submitted student paper and not an official Liberty University document. Read it for structure and reasoning, then write your own to the instructions in your Canvas course. If you want a version built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.