This BUSI 615 Week 8 sample is the written management report for the Final Integrated Learning Project, the 200-point deliverable that accompanies a team's working Excel ERP model. Written for the owners of a composite Pennsylvania stove maker, it summarizes what the model's master production schedule, bill of materials, MRP, capacity, distribution and transport modules showed, then answers the three questions Liberty's guide sets: whether to implement, based on a five-year cost-benefit analysis with a net present value and sensitivity tests; how to implement, through a phased plan with named responsibilities; and which ERP system to choose and how to run it, cloud or local, national or global. Research on enterprise system returns, cloud ERP in smaller firms and implementation success supports the choices. Liberty University BUSI 615 closes its MBA logistics course with this project.

CourseBUSI 615 Logistics (BUSI615)
Module/Week8
AssignmentFinal Integrated Learning Project management report
Paper typeManagement report accompanying an Excel ERP model
Lengthabout 1,588 words, 6 double-spaced pages plus title page and references. Course guide: a written management report submitted with the team's working Excel ERP model, covering a cost-benefit recommendation, an implementation project plan with responsibilities and a justified ERP system and operating recommendation
FormatAPA 7 student paper
Points200
SchoolLiberty University Online
ProgramMBA
Where it sitsModule/Week 8 in Liberty's published BUSI 615 course guide; current sections can differ
UpdatedOctober 2026

Free sample paper for BUSI 615 Week 8

1

An Integrated ERP Plan for Harlan Ridge Stoveworks: Cost-Benefit Case, Implementation Plan and System Recommendation

 

[Student Name]

School of Business, Liberty University

BUSI 615: Logistics

Final Integrated Learning Project: Management Report

[Instructor Name]

[Date]

 

The stove manufacturer, its Excel model results and all cost and benefit figures are composites standing in for a team's chosen firm and spreadsheet; the vendor shortlist names real products, the scores are illustrative, the research cited is real, and the requirements follow Liberty's public course guide for BUSI 615.

2

An Integrated ERP Plan for Harlan Ridge Stoveworks: Cost-Benefit Case, Implementation Plan and System Recommendation

Executive Summary

Why this part earns its pointsThe summary gives the decision, the money and the main condition in the first paragraph, which is what owners read first.
3

We recommend that Harlan Ridge Stoveworks implement a cloud-based enterprise resource planning (ERP) system, going live in April with a single national instance, and that the owners approve a one-time budget of $1.17 million including contingency. Over five years, the investment has an estimated net present value of $1.78 million at a 10 percent discount rate and pays back in just over two years. It remains positive even if benefits fall 40 percent short of our estimates. The main condition is that the preparation phase reaches 95 percent inventory record accuracy before the system goes live; without accurate records, the benefits in this report will not appear.

Our Excel model, submitted with this report, links six planning modules for the firm's two product families. Its results show that integrated planning would let the plant build ahead of the heating season more evenly, carry about $2.2 million less inventory on average and cut the emergency freight and peak-season overtime that currently absorb much of the firm's margin.

What the Model Shows

Harlan Ridge is a composite stove maker in Lancaster County, Pennsylvania, building wood and pellet models with about 240 employees, annual sales of roughly $68 million and two regional warehouses, in Columbus, Ohio, and Albany, New York, serving about 600 hearth dealers. About 70 percent of shipments leave between September and December. Planning today relies on a legacy order-entry program, spreadsheets in the plant and a separate accounting package.

The master production schedule module levels production across the year, building pellet stoves at a steady rate from March and adding a second shift only in August and September instead of from July. The bill of materials and MRP modules show that 14 long-lead components, chiefly auger motors, control boards and ceramic glass, account for most of the shortages the plant suffered last season; all 14 now receive planned orders timed to supplier lead times. The capacity planning module identifies the powder-coat paint line as the binding constraint in August, when the leveled schedule still loads it to 104 percent of capacity, so we recommend a weekend paint shift that month. The distribution requirements planning module plans weekly mixed-model trailers to both warehouses, replacing fortnightly single-model loads, and the transport requirements planning module converts those shipments into 11 fewer emergency less-than-truckload shipments per month during the peak.

The model's main finding is not that the firm needs more stock or more capacity, but that it needs to use the capacity it already has earlier in the year.

Cost-Benefit Analysis

Why this part earns its pointsEvery figure in the table is traceable to an assumption stated in the text, so the owners can change any one and see its effect.
4

We estimated costs from vendor demonstrations and quotations obtained by the team and benefits from the Excel model's comparison of current practice with integrated planning. One-time costs total $1.02 million: $650,000 for an implementation partner to configure the system and convert data, $220,000 for internal staff time and temporary backfill during data cleanup, $60,000 for training and $90,000 to connect a dealer ordering portal and our two carriers. We add a 15 percent contingency of $153,000. Recurring costs are $180,000 a year in subscription fees for about 85 named users and $95,000 for an internal ERP analyst.

Benefits at full run rate total $1.24 million a year: $440,000 in lower inventory carrying cost, from a $2.2 million reduction in average inventory at a 20 percent carrying rate; $168,000 from a 40 percent reduction in expedited freight; $260,000 in avoided peak-season overtime; $290,000 in contribution from recovered sales, which is half the margin on the roughly 900 stoves dealers could not obtain last season, discounted because some would have been lost anyway; and $85,000 from retiring the legacy systems. We assume only 50 percent of these benefits in the first year, while the system is new, and 85 percent in the second.

Year012345
One-time costs, including contingency ($000)(1,173)
Benefits ($000)6221,0571,2431,2431,243
Recurring costs ($000)(275)(275)(275)(275)(275)
Net cash flow ($000)(1,173)347782968968968

Discounting each year's net figure at 10 percent yields a net present value near $1.78 million, and the cumulative cash turns positive after about 2.0 years. The $2.2 million reduction in inventory also releases cash once, which we have not counted as a benefit beyond its carrying cost, so the estimate is conservative in that respect.

We tested three downside cases. If every benefit stream is 40 percent smaller than estimated, the net present value falls to about $180,000 and payback lengthens to about 3.5 years. If one-time costs overrun by 50 percent, the value is about $1.19 million. If go-live slips a full year so that benefits start one year late, the value is about $710,000. The project therefore survives each risk on its own, although a combination of weak benefits and a large overrun would leave it close to break-even. This pattern is consistent with research on enterprise systems: in a study of 186 announced ERP implementations, Hendricks et al. (2007) found some evidence of improved profitability, especially among early adopters, without persistent evidence that the investments harmed performance. Returns are possible but not automatic, which is why our plan ties spending to exit tests.

Recommendation on Implementation

We recommend proceeding. The benefits rest mainly on operational changes the model has shown to be feasible, leveling production, timing long-lead purchases and shipping smaller mixed loads, rather than on intangible gains such as "better visibility." The largest single benefit, lower carrying cost, follows directly from planning that the firm cannot do reliably with spreadsheets. We do not recommend the alternative of extending the current spreadsheets, because they cannot net requirements across 14 long-lead components and two warehouses fast enough to replan when a supplier ships late, which is when they are most needed.

Implementation Project Plan and Responsibilities

Why this part earns its pointsThe plan assigns each phase to a named role with a test it must pass, which turns the forum's discussion of success factors into accountability.
5

The implementation follows four phases, each closing with an exit test, and is timed so the firm never changes systems during the heating season. Markus et al. (2000) found that success in ERP projects depends on when it is measured and that many problems seen late in a project began early without being noticed. Our plan therefore measures each phase on its own terms, with particular attention to the summer shakedown before the first peak season on the new system.

Phase and timingMain tasksResponsibleExit test
Preparation, October to FebruarySelect vendor and partner; clean item, bill of materials and dealer records; configure; train key usersExecutive sponsor: owner. Project manager: operations manager. Data: materials manager. Training: implementation partner95 percent inventory record accuracy; bills verified for all active models
Pilot, MarchRun the wood stove family end to end on the new systemProduction planner with partner consultantTwo weeks of correct plans and shipments for the pilot family
Cutover, AprilMove pellet stoves, purchasing, warehouses and finance; reconcile open orders and balancesProject manager; controller for finance data; warehouse leads for stockMonth-end close within five working days; open orders reconciled to the dollar
Shakedown, May to AugustFix errors; tune MRP and DRP settings; measure weeklyERP analyst; planners; buyersFewer than 10 percent of planned orders changed manually; no system-caused emergency shipments for 30 days

The owner acts as executive sponsor and decides on scope changes and any delay to the go-live date. The operations manager runs the project day to day and reports progress to the owner every two weeks against the exit tests. The materials manager owns data quality, which Umble et al. (2003) identified as a critical success factor along with top management commitment, a capable team and extensive education. Department heads release their staff for training, and the new ERP analyst, hired at the start of preparation, becomes the long-term owner of the system once the partner leaves.

ERP System Recommendation

We compared three mid-market systems that are sold to manufacturers of Harlan Ridge's size: Epicor Kinetic, Microsoft Dynamics 365 Business Central and SAP Business One. The team scored each from vendor demonstrations against criteria drawn from the model's findings.

Criterion (weight)Epicor KineticDynamics 365 Business CentralSAP Business One
Discrete manufacturing MRP and capacity planning (30%)534
Multi-warehouse distribution planning (20%)443
Dealer portal and carrier integration (15%)453
Five-year cost (20%)344
Partner availability in the region (15%)453
Weighted score (out of 5)4.104.003.50

On these scores, Epicor Kinetic and Business Central are nearly tied, and the deciding factor is the first criterion, which carries the largest weight because the model showed that the firm's main problem is planning long-lead materials against a seasonal schedule. We therefore recommend Epicor Kinetic, subject to a scripted demonstration in which the vendor runs our own pellet stove bill of materials and leveled schedule. If it fails that test, Business Central becomes the recommendation.

Operation and Scope

We recommend cloud operation. Harlan Ridge has two IT staff and no data center, and running servers locally would require hardware, backups and security expertise the firm does not have. Gupta et al. (2018) note that cloud ERP lets smaller firms avoid large budgets for infrastructure and specialist personnel, and their survey of 208 small and medium firms linked successful cloud ERP to factors on the provider's side, namely compliance, network performance and information security. Our plan addresses those factors by requiring the vendor's independent security audit reports before signing and by adding a second internet connection at the plant so that a single line outage cannot stop shipping.

The scope should be national with a single instance. All of Harlan Ridge's operations and customers are in the United States, so one company, one currency for sales and one set of books suffice. The firm does buy auger motors and some glass from overseas suppliers, so the system must handle purchase orders in foreign currencies and long ocean lead times, which all three candidates support. A global configuration with multiple legal entities would add cost and complexity with no current benefit, though a single cloud instance can be extended later if the firm opens a Canadian warehouse, which the owners have discussed.

Risks and Conditions

Three risks deserve the owners' attention. The first is data: if record accuracy has not reached 95 percent by February, the go-live should move to the following April rather than proceed, since the one-year delay case still shows positive value while a failed peak season would not. The second is customization: every request to change the software to preserve an old practice should go to the owner for approval, because changes raise cost and complicate upgrades. The third is people: planners who distrust the system will override it, so the shakedown measures include the share of orders changed manually as an early warning.

Conclusion

The Excel model shows that Harlan Ridge's chronic peak-season problems come from planning too late with too little information, not from a lack of capacity. An integrated cloud ERP, implemented in the off-season with tested phases and clear owners, addresses that cause at an acceptable cost and with a margin of safety in the financial case. We recommend that the owners approve the budget, appoint the operations manager as project manager and begin vendor demonstrations in October.

6

References

Gupta, S., Misra, S. C., Kock, N., & Roubaud, D. (2018). Organizational, technological and extrinsic factors in the implementation of cloud ERP in SMEs. Journal of Organizational Change Management, 31(1), 83-102. https://doi.org/10.1108/JOCM-06-2017-0230

Hendricks, K. B., Singhal, V. R., & Stratman, J. K. (2007). The impact of enterprise systems on corporate performance: A study of ERP, SCM, and CRM system implementations. Journal of Operations Management, 25(1), 65-82. https://doi.org/10.1016/j.jom.2006.02.002

Markus, M. L., Axline, S., Petrie, D., & Tanis, C. (2000). Learning from adopters' experiences with ERP: Problems encountered and success achieved. Journal of Information Technology, 15(4), 245-265. https://doi.org/10.1080/02683960010008944

Umble, E. J., Haft, R. R., & Umble, M. M. (2003). Enterprise resource planning: Implementation procedures and critical success factors. European Journal of Operational Research, 146(2), 241-257. https://doi.org/10.1016/S0377-2217(02)00547-7

What the BUSI 615 Week 8 instructions ask

Module/Week 8 of BUSI 615 brings the Final Integrated Learning Project, worth 200 points, the heaviest item in the grading table. Teams submit a working ERP model in Excel that ties the weekly modules together: master production schedule, bill of materials, materials requirements planning, capacity planning, distribution requirements planning and transport requirements planning. A management report goes with it, and the guide lists what that report must contain: a recommendation on implementation based on cost and benefits, an implementation project plan that assigns responsibilities and a justified recommendation for an ERP system, such as SAP or another package, including whether it runs locally or in the cloud and its scope, national or global. A Kaltura presentation in the course content gives further detail. The last Discussion Board 4 replies are due that same week.

How this BUSI 615 Week 8 example is built

Like a consulting deliverable, the report leads with its answer. An executive summary gives the recommendation and the headline numbers, and a short section translates the Excel model's results into business terms, such as the inventory the plan releases. The cost-benefit section sets one-time and recurring costs against five benefit streams, discounts them at 10 percent and tests what happens if benefits fall short or costs overrun. The implementation plan reuses the phased, off-season approach from the Week 7 forum, now with a responsibility table. A weighted comparison of three mid-market systems leads to a cloud recommendation with a single national instance, and the report closes with the conditions under which the owners should stop or delay.

BUSI 615 Week 8 grading rubric: where the points go

The final project's 200 points cover both the Excel model and this report, so the report is judged on how well it uses the model. A strong report states the recommendation plainly, shows the cost-benefit arithmetic with its assumptions visible and tests the result against plausible errors rather than presenting one optimistic figure. The implementation plan should have phases, timing and named responsibilities, not just a list of success factors. The ERP recommendation must be justified against criteria tied to the firm's needs, and the choice of cloud or local operation and of national or global scope must follow from the firm's situation. Professional business writing, accurate use of course terms and APA citations are expected throughout.

BUSI 615 Week 8 help: mistakes that cost points

Final reports lose points most often by restating the spreadsheet instead of interpreting it. Owners need to know what the MRP and DRP results mean for cash, service and workload, so translate every module into one or two business consequences. Show the cost-benefit math in a table and label every assumption; graders check that totals and the net present value can be traced. Include at least one downside case. Avoid recommending a vendor because it is well known: score candidates against criteria that come from your firm, such as discrete manufacturing depth or dealer integration. Assign responsibilities to roles, not to "the team." Finally, make sure the report and the Excel model use the same figures, since inconsistencies between them are easy for an instructor to spot.

Related BUSI 615 sample papers

Other BUSI 615 weeks

More MBA sample papers

BUSI 615 Week 8 questions, answered

What is the BUSI 615 Final Integrated Learning Project?

A 200-point team project due in Module/Week 8: a working Excel ERP model tying together the MPS, bill of materials, MRP, capacity, distribution and transport modules, plus a written management report with a cost-benefit recommendation, implementation plan and ERP system recommendation.

Where can I find a free BUSI 615 Week 8 sample paper?

The full management report for the BUSI 615 Week 8 final project is on this page, with a five-year cost-benefit table, a phased implementation plan with responsibilities and a cloud ERP recommendation for a composite stove maker.

How do you do a cost-benefit analysis for an ERP system?

List one-time costs such as implementation services, data cleanup, training and contingency, recurring costs such as subscriptions and support, and benefit streams such as lower carrying cost and freight, then discount the yearly net figures and test the result under weaker assumptions.

Should a small manufacturer choose cloud or on-premise ERP?

Cloud ERP avoids buying servers and hiring specialist IT staff, which suits many smaller firms, but it depends on reliable network access, the provider's security and compliance and limits on customization, so the choice should follow from those conditions.

What does the BUSI 615 Excel ERP model include?

The guide lists six integrated modules: master production schedule, bill of materials, materials requirements planning, capacity planning, distribution requirements planning and transport requirements planning, built up through the weekly team projects.

Use it as a model, or ask for your own

This paper is an original model written by our desk for study. It is not a submitted student paper and not an official Liberty University document. Read it for structure and reasoning, then write your own to the instructions in your Canvas course. If you want a version built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.